355 S OGDEN DR 90036
Certificate Information: 355 S OGDEN DR 90036
- Application / Permit
- 21020-10000-02605
- Plan Check / Job No.
- B21LA21546
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- Early start permit forTemporary shoring with lagging & soldier piles for new 8-story mixed use apartment building over 2 levels of subterrenean parking garage . (5 story type III-A over 3 levels of Type I-A above grade parking and 2 levels of subterrenean parking). ( Building permit application # 21010-10000-05966).
- Permit Issued
- Issued on 12/22/2022
- Issuing Office
- Current Status
- Issued on 12/22/2022
Permit Application Status History
| Submitted | 11/23/2021 | APPLICANT |
| Green Plans Picked Up | 12/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2021 | GARO TELMI |
| Disabled Access Plans Picked Up | 12/16/2021 | APPLICANT |
| Corrections Issued | 1/5/2022 | GARO TELMI |
| Quality Review Completed | 1/13/2022 | KEN GILL |
| Building Plans Picked Up | 1/18/2022 | APPLICANT |
| Applicant returned to address corrections | 2/7/2022 | GARO TELMI |
| Applicant returned to address corrections | 2/11/2022 | GARO TELMI |
| Applicant returned to address corrections | 3/10/2022 | GARO TELMI |
| Applicant returned to address corrections | 3/24/2022 | GARO TELMI |
| Applicant returned to address corrections | 4/7/2022 | GARO TELMI |
| Applicant returned to address corrections | 5/5/2022 | GARO TELMI |
| Applicant returned to address corrections | 9/21/2022 | GARO TELMI |
| Applicant returned to address corrections | 12/7/2022 | GARO TELMI |
| Plan Check Approved | 12/22/2022 | GARO TELMI |
| Issued | 12/22/2022 | APPLICANT |
Permit Application Clearance Information
| Abandoned oil well | Cleared | 7/14/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 8/1/2022 | ORVAL HERNANDEZ-MARCI |
| Stormwater Pollution Mitigatn | Cleared | 8/1/2022 | ORVAL HERNANDEZ-MARCI |
| DAS Clearance | Cleared | 8/7/2022 | GARO TELMI |
| Construction near power lines | Cleared | 8/10/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/10/2022 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2022 | CINDY QI |
| Certificate of Compliance | Cleared | 9/14/2022 | LOUIS ORTEGA |
| Fire Marshal Fire Life Safety | Cleared | 9/20/2022 | WILLIAM JOHNS |
| CPC | Cleared | 10/12/2022 | BOB BABAJIAN |
| Miscellaneous | Cleared | 10/12/2022 | BOB BABAJIAN |
| Miscellaneous | Cleared | 10/12/2022 | BOB BABAJIAN |
| Site Plan review | Cleared | 10/12/2022 | BOB BABAJIAN |
| Miscellaneous | Cleared | 11/17/2022 | BOB BABAJIAN |
| Work Adjacent to Public Way | Cleared | 12/19/2022 | JOSE RODRIGUEZ |
| Work Adjacent to Public Way | Cleared | 12/19/2022 | JOSE RODRIGUEZ |
| Miscellaneous | Cleared | 12/20/2022 | ROBIN ETNIEL |
| Excavation more than 5-ft deep | Cleared | 12/22/2022 | CALOSHA APPROVED |
Contact Information
| Contractor | Holland Construction Inc; Lic. No.: 944880-B | 1111 MAIN STREET STE 700 VANCOUVER, WA 98660 |
| Engineer | Adams,, Jelisa; Lic. No.: GE3092 | 26632 EL TOBOSO MISSION VIEJO, CA 92691 |
| Engineer | Cefali,, David Allen; Lic. No.: S3658 | 4344 LAUREL CANYON BLVD_STE 3 STUDIO CITY, CA 91604 |
| Engineer | Johnson,, Jeremy Allen; Lic. No.: C71475 | 28363 BERYLWOOD PL VALENCIA, CA 91354 |
Inspector Information
| MARTIN TAVITIAN, (213) 482-7357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/23/2023 | Approved | EDWIN GREGORYONA |
| Deputy Steel/Welding | 1/31/2023 | Partial Approval | ALFREDO LOPEZ |
| Deputy Steel/Welding | 2/1/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 2/6/2023 | Partial Approval | ALFREDO LOPEZ |
| Deputy Reinf. Concrete | 2/6/2023 | Partial Approval | ALFREDO LOPEZ |
| Deputy Steel/Welding | 2/6/2023 | Partial Approval | ALFREDO LOPEZ |
| Deputy Grading | 2/7/2023 | Partial Approval | ALFREDO LOPEZ |
| Deputy Reinf. Concrete | 2/7/2023 | Partial Approval | ALFREDO LOPEZ |
| Deputy Steel/Welding | 2/7/2023 | Partial Approval | ALFREDO LOPEZ |
| Deputy Grading | 2/8/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 2/8/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 2/8/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 2/9/2023 | Partial Approval | ALFREDO LOPEZ |
| Deputy Grading | 2/10/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 2/10/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 2/10/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 2/13/2023 | Partial Approval | ALFREDO LOPEZ |
| Deputy Steel/Welding | 2/13/2023 | Partial Approval | ALFREDO LOPEZ |
| Deputy Grading | 2/14/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 2/14/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 2/15/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 2/15/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 2/16/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 2/16/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 2/17/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 2/17/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 2/21/2023 | Partial Approval | ALFREDO LOPEZ |
| Deputy Grading | 2/22/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 2/23/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 2/27/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 2/27/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 2/28/2023 | Partial Approval | ALFREDO LOPEZ |
| Deputy Reinf. Concrete | 2/28/2023 | Partial Approval | ALFREDO LOPEZ |
| Deputy Grading | 3/2/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 3/2/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 3/6/2023 | Conditional Approval | RONALD JIMENEZ |
| Deputy Reinf. Concrete | 3/6/2023 | Conditional Approval | RONALD JIMENEZ |
| Deputy Grading | 3/7/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 3/8/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 3/9/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 3/13/2023 | Partial Approval | EDWIN GREGORYONA |
| Excavation/Setback/Form/Re-Bar | 3/13/2023 | Partial Inspection | EDWIN GREGORYONA |
| Deputy Grading | 3/14/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 3/15/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 3/16/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 3/17/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 3/20/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 3/21/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 3/22/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 3/23/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 3/24/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 3/31/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 3/31/2023 | Partial Approval | EDWIN GREGORYONA |
| Excavation/Setback/Form/Re-Bar | 3/31/2023 | Partial Inspection | EDWIN GREGORYONA |
| Deputy Grading | 4/3/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 4/7/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 4/10/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 4/14/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Excavation/Setback/Form/Re-Bar | 4/14/2023 | Partial Inspection | EDWIN GREGORYONA |
| Deputy Grading | 4/17/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 4/26/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 4/26/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 4/27/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 4/28/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Excavation/Setback/Form/Re-Bar | 4/28/2023 | Partial Inspection | TIMOTHY POWELL |
| Deputy Grading | 5/1/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/2/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 5/3/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 5/4/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 5/4/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/5/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 5/5/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 5/5/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/8/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 5/8/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 5/8/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 5/9/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 5/9/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 5/9/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/10/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 5/10/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 5/10/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/11/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 5/11/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 5/11/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/12/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 5/12/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 5/12/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/15/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 5/15/2023 | Partial Approval | EDWIN GREGORYONA |
| Excavation/Setback/Form/Re-Bar | 5/15/2023 | Partial Inspection | EDWIN GREGORYONA |
| Deputy Grading | 5/16/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/17/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/18/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 5/18/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 5/18/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/19/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 5/19/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/23/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 5/23/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 5/24/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 5/25/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 5/30/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 5/31/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 6/1/2023 | Partial Approval | EDWIN GREGORYONA |
| Excavation/Setback/Form/Re-Bar | 6/1/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 6/2/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 6/5/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 6/6/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 6/7/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 6/7/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 6/9/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 6/13/2023 | Partial Approval | EDWIN GREGORYONA |
| Excavation/Setback/Form/Re-Bar | 6/16/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 6/20/2023 | Conditional Approval | GREGORY POMISH |
| Deputy Steel/Welding | 6/20/2023 | Conditional Approval | GREGORY POMISH |
| Deputy Grading | 6/21/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 6/21/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 6/27/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 6/27/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 6/28/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 6/28/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 7/5/2023 | Partial Approval | EDWIN GREGORYONA |
| Excavation/Setback/Form/Re-Bar | 7/5/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 7/11/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 7/21/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 7/24/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 7/25/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 9/13/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 10/17/2023 | Conditional Approval | GREGORY POMISH |
| Deputy Grading | 10/18/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 10/19/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 10/31/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 7/30/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 7/31/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 8/1/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 8/6/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 8/8/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 8/9/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 8/13/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 8/13/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 8/19/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 8/26/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 1/21/2025 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 2/5/2025 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 2/11/2025 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 2/20/2025 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 2/21/2025 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 2/24/2025 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 2/25/2025 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 10/27/2025 | Partial Approval | EDWIN GREGORYONA |