1169 N ANGELO DR 90210
Certificate Information: 1169 N ANGELO DR 90210
- Application / Permit
- 21020-10000-02515
- Plan Check / Job No.
- B21LA20745
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW DECK ATTACHED TO (E) SFD
- Permit Issued
- Issued on 4/5/2022
- Issuing Office
- Current Status
- Permit Finaled on 1/13/2023
Permit Application Status History
| Submitted | 11/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2021 | CARLOS MONTES |
| Corrections Issued | 12/9/2021 | CARLOS MONTES |
| Quality Review Completed | 12/15/2021 | KEN GILL |
| Applicant returned to address corrections | 2/25/2022 | CARLOS MONTES |
| Plan Check Approved | 3/31/2022 | CARLOS MONTES |
| Issued | 4/5/2022 | APPLICANT |
| Building Plans Picked Up | 4/7/2022 | APPLICANT |
| Permit Finaled | 12/9/2022 | GERMAN RODRIGUEZ MENDOZA |
| CofO in Progress | 12/12/2022 | GERMAN RODRIGUEZ MENDOZA |
| No Progress | 1/13/2023 | MICHAEL PELHAM |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 1/10/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 1/10/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 1/10/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 1/10/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 1/10/2022 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 1/10/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2022 | DINAH GARIN |
| Construction near power lines | Cleared | 3/15/2022 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 3/16/2022 | VASIL MIHALEV |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Aronianpour,, Eilan; Lic. No.: C88101 | 7242 JELLICO AVE LAKE BALBOA, CA 91406 |
| Engineer | Cai,, Luo B; Lic. No.: C80352 | 9428 ETAON AVE M CHATSWORTH, CA 91311 |
| Geologist | Tsao,, Tze-Tzong; Lic. No.: EG1783 | 9428 ETON AVENUE #M CHATSWORTH, CA 91311 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 6/22/2022 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Pre-Inspection | 6/22/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Deputy Reinf. Concrete | 7/6/2022 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Excavation/Setback/Form/Re-Bar | 7/13/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 8/29/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Piling/Pier/Caisson | 8/29/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Rough-Elec/Plmb/HVAC | 8/29/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Excavation/Setback/Form/Re-Bar | 8/31/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 8/31/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Structural Steel Frame | 8/31/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 8/31/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Excavation/Setback/Form/Re-Bar | 10/11/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 10/11/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Gas Test | 10/11/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 10/11/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Structural Steel Frame | 10/11/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Excavation/Setback/Form/Re-Bar | 10/13/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Gas Test | 10/13/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 11/1/2022 | Approved | CHRISTOPHER WILSON |
| Deputy Steel/Welding | 11/1/2022 | Conditional Approval | MICHAEL PELHAM |
| ELECTRICAL-Rough | 11/1/2022 | Partial Approval | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2022 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Rough | 11/1/2022 | Partial Approval | CHRISTOPHER WILSON |
| Structural Steel Frame | 11/1/2022 | Partial Approval | CHRISTOPHER WILSON |
| Final | 11/5/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 11/5/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 11/5/2022 | SGSOV Not Ready | CHRISTOPHER WILSON |
| Smoke Detectors | 11/5/2022 | Approved | CHRISTOPHER WILSON |
| Final | 12/9/2022 | Permit Finaled | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 12/9/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 12/9/2022 | SGSOV Approved | GERMAN RODRIGUEZ MENDOZA |