10602 N FERNGLEN AVE 91042
Certificate Information: 10602 N FERNGLEN AVE 91042
- Application / Permit
- 21020-10000-02462
- Plan Check / Job No.
- B21LA20413
- Group
- Building
- Type
- Nonbldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- REPLACEMENT OF (E) RETAINING WALL. NEW RETAINING WALL TO BE APPROXIMATELY 6 FEET HIGH FROM BOTTOM OF FOOTING, WITH A TOTAL LENGTH OF 30'-9" "COMPLY WITH DEPARTMENT ORDER effective date 04/26/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE" 1 OF 2
- Permit Issued
- Issued on 4/1/2022
- Issuing Office
- Current Status
- Permit Finaled on 7/30/2024
Permit Application Status History
| Submitted | 10/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 12/1/2021 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 12/2/2021 | SAI KHUM |
| Applicant returned to address corrections | 3/3/2022 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 3/24/2022 | FARSHAD ALIMOHAMADI |
| Issued | 4/1/2022 | APPLICANT |
| Building Plans Picked Up | 4/4/2022 | APPLICANT |
| Permit Finaled | 7/29/2024 | CHARLES POWELL |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/4/2022 | TINA MIRANDA |
Contact Information
| Contractor | Coast Construction And Foundation Repair Inc; Lic. No.: 1007583-A | 302 FRASER LANE VENTURA, CA 93001 |
| Engineer | Morales,, Cesar Del Valle; Lic. No.: C76612 | 11735 THORSON AVE LYNWOOD, CA 90262 |
Inspector Information
| BRIAN MILLER, (818) 374-4359 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/26/2022 | Not Ready for Inspection | LANNY MERRICK |
| Excavation/Setback/Form/Re-Bar | 5/2/2022 | Partial Approval | LANNY MERRICK |
| Deputy Reinf. Concrete | 5/3/2022 | Partial Approval | MATTHEW NELSON |
| Deputy Reinf. Concrete | 5/17/2022 | Conditional Approval | DAVID MATSON |
| Deputy Reinf. Masonry | 5/19/2022 | Conditional Approval | MATTHEW NELSON |
| Masonry Wall/Backfill | 5/19/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 5/31/2022 | Approved | LANNY MERRICK |
| Deputy Reinf. Masonry | 6/2/2022 | Conditional Approval | DAVID MATSON |
| Masonry Wall/Backfill | 6/3/2022 | Partial Approval | LANNY MERRICK |
| Reinforced Masonry Frame | 6/3/2022 | Partial Approval | LANNY MERRICK |
| Final | 7/29/2024 | Permit Finaled | CHARLES POWELL |