641 N WESTERN AVE 90004
Certificate Information: 641 N WESTERN AVE 90004
- Application / Permit
- 21020-10000-02414
- Plan Check / Job No.
- B21LA19941
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- ePlan NEW CMU TRASH ENCLOSURE,
- Permit Issued
- Issued on 5/18/2022
- Issuing Office
- Current Status
- CofO Issued on 9/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2021 | HERNAN ARREOLA |
| Corrections Issued | 10/30/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 12/6/2021 | HERNAN ARREOLA |
| Plan Check Approved | 5/12/2022 | HERNAN ARREOLA |
| Issued | 5/18/2022 | APPLICANT |
| CofO in Progress | 9/22/2023 | RONALD JIMENEZ |
| CofO Issued | 9/22/2023 | ERNESTO CORRAL |
| Permit Finaled | 9/22/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| Redevelopment Project Area | Cleared | 12/30/2021 | DAVID URITA |
Contact Information
| Architect | Liljegren,, Karin J; Lic. No.: NA28158 | , |
| Contractor | M D M Builders Group; Lic. No.: 933238-B | , |
| Contractor | M Librush Construction Inc; Lic. No.: 933238-B | , |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/16/2023 | Approved | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 5/4/2023 | Partial Approval | KATY RAMIREZ |
| Masonry Wall/Backfill | 5/10/2023 | Partial Approval | TIMOTHY POWELL |
| Deputy Reinf. Masonry | 5/12/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Footing/Foundation/Slab | 5/19/2023 | Approved | MARTIN TAVITIAN |
| Final | 7/6/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Final | 8/14/2023 | Conditional Approval | RONALD JIMENEZ |