3912 S BURNSIDE AVE 90008
Certificate Information: 3912 S BURNSIDE AVE 90008
- Application / Permit
- 21020-10000-02336
- Plan Check / Job No.
- B21LA19244
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- (N) RETAINING WALLS IN REAR YARD (MAX. 6-FT HIGH AND TOTAL 47-FT LONG) AND IN SIDE YARD (MAX. 9-FT HIGH AND TOTAL 122-FT LONG). 3 OF 4
- Permit Issued
- Issued on 6/12/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 12/8/2025
Permit Application Status History
| Submitted | 10/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | CHUNG-WEN CHUANG |
| Corrections Issued | 12/6/2021 | CHUNG-WEN CHUANG |
| Quality Review Completed | 12/15/2021 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 12/20/2021 | APPLICANT |
| Applicant returned to address corrections | 7/11/2022 | CHUNG-WEN CHUANG |
| Plan Check Approved | 1/9/2023 | CHUNG-WEN CHUANG |
| Issued | 6/12/2023 | APPLICANT |
| Permit Finaled-Status Void | 12/5/2025 | MICHAEL TEMPLE |
| Permit Finaled | 12/5/2025 | MICHAEL TEMPLE |
| Re-Activate Permit | 12/8/2025 | MICHAEL TEMPLE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 7/13/2022 | RIDWAN HARDY |
| Excavation more than 5-ft deep | Cleared | 9/7/2022 | CALOSHA APPROVED |
Contact Information
| Architect | Jacobs,, Michael Christopher; Lic. No.: C29962 | 25 HOPKE AVENUE HASTINGS ON HUDSON, NY 10706 |
| Contractor | Owner-Builder | , |
| Engineer | Cai,, Luo B; Lic. No.: C80352 | 9428 ETAON AVE M CHATSWORTH, CA 91311 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Engineer | Tsao,, Tze-Tzong; Lic. No.: C46886 | 9428 ETON AVE STE M CHATSWORTH, CA 91311 |
| Geologist | Tsao,, Tze-Tzong; Lic. No.: EG1783 | 9428 ETON AVENUE #M CHATSWORTH, CA 91311 |
Inspector Information
| AL GAMBLE, (213) 482-0403 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/18/2023 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 3/4/2024 | Partial Inspection | JONATHAN HOM |
| Footing/Foundation/Slab | 3/6/2024 | Partial Inspection | JONATHAN HOM |
| Masonry Wall/Backfill | 3/13/2024 | Not Ready for Inspection | JONATHAN HOM |
| Masonry Wall/Backfill | 3/14/2024 | Partial Approval | JONATHAN HOM |
| Masonry Wall/Backfill | 3/19/2024 | Partial Approval | JONATHAN HOM |
| Special/Order Compliance | 3/22/2024 | Corrections Issued | JONATHAN HOM |
| Footing/Foundation/Slab | 4/5/2024 | Conditional Approval | MATTHEW JENKINS |
| Masonry Wall/Backfill | 4/5/2024 | Conditional Approval | MATTHEW JENKINS |
| Masonry Wall/Backfill | 4/9/2024 | Partial Approval | JONATHAN HOM |
| Masonry Wall/Backfill | 4/10/2024 | Partial Inspection | JONATHAN HOM |
| Masonry Wall/Backfill | 4/11/2024 | Partial Approval | JONATHAN HOM |
| Footing/Foundation/Slab | 4/22/2024 | Partial Inspection | JONATHAN HOM |
| Footing/Foundation/Slab | 4/23/2024 | Corrections Issued | JONATHAN HOM |
| Footing/Foundation/Slab | 4/24/2024 | Partial Approval | JONATHAN HOM |
| Masonry Wall/Backfill | 4/26/2024 | Approved | JONATHAN HOM |
| Footing/Foundation/Slab | 5/2/2024 | Partial Approval | JONATHAN HOM |
| Footing/Foundation/Slab | 5/3/2024 | Partial Approval | RUSSELL BONVOULOIR |
| Masonry Wall/Backfill | 5/6/2024 | Partial Inspection | RUSSELL BONVOULOIR |
| Reinforced Concrete Frame | 5/6/2024 | Corrections Issued | RUSSELL BONVOULOIR |
| Masonry Wall/Backfill | 5/9/2024 | Partial Approval | JONATHAN HOM |
| Footing/Foundation/Slab | 5/14/2024 | Partial Inspection | JONATHAN HOM |
| Footing/Foundation/Slab | 5/15/2024 | Partial Approval | JONATHAN HOM |
| Masonry Wall/Backfill | 5/16/2024 | Partial Approval | JONATHAN HOM |
| Reinforced Concrete Frame | 5/16/2024 | Partial Inspection | JONATHAN HOM |
| Final | 11/19/2025 | Corrections Issued | ROBERT PINA |
| Final | 11/26/2025 | Partial Inspection | AL GAMBLE |
| Final | 12/5/2025 | Permit Finaled | MICHAEL TEMPLE |