402 S LAS PALMAS AVE 90020

Certificate Information: 402 S LAS PALMAS AVE 90020

Application / Permit
21020-10000-02255
Plan Check / Job No.
B21LA16384
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Shoring (Temporary)
Work Description
Temporary shoring
Permit Issued
Issued on 2/10/2022
Issuing Office
Current Status
Permit Finaled on 3/26/2026

Permit Application Status History

Submitted 8/31/2021 APPLICANT
Assigned to Plan Check Engineer 9/30/2021 VU NGUYEN
Corrections Issued 10/5/2021 VU NGUYEN
Quality Review Completed 10/6/2021 EUGENE BARBEAU
Building Plans Picked Up 10/8/2021 APPLICANT
Applicant returned to address corrections 1/25/2022 VU NGUYEN
Applicant returned to address corrections 1/31/2022 VU NGUYEN
Plan Check Approved 2/10/2022 VU NGUYEN
Issued 2/10/2022 APPLICANT
Permit Finaled 3/26/2026 RONNIE MINDANAO

Permit Application Clearance Information

CPC Cleared 10/29/2021 SUKI GERSHENHORN
CPC Cleared 10/29/2021 SUKI GERSHENHORN
HPOZ Cleared 10/29/2021 SUKI GERSHENHORN
Miscellaneous Cleared 10/29/2021 SUKI GERSHENHORN

Contact Information

Contractor Hartman Baldwin Inc; Lic. No.: 653340-B 100 WEST FOOTHILL BLVD      CLAREMONT, CA 91711
Engineer Hollingsworth,, Robert Alan; Lic. No.: GE2022 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362
Engineer Mahlow,, Elizabeth Joy Johnson; Lic. No.: C80463 600 WILSHIRE BLVD   SUITE 760    LOS ANGELES, CA 90065

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 3/17/2022 Approved ARTHUR SARGSYAN
Deputy Grading 3/23/2022 Approved ARTHUR SARGSYAN
Deputy Reinf. Concrete 3/23/2022 Approved ARTHUR SARGSYAN
Deputy Grading 3/31/2022 Conditional Approval CRAIG DAVIS
SUSMP-Std. Urban Storm Water 4/1/2022 Not Ready for Inspection CRAIG DAVIS
Final 3/26/2026 Permit Finaled RONNIE MINDANAO