3545 W WILSHIRE BLVD 90010

Certificate Information: 3545 W WILSHIRE BLVD 90010

Application / Permit
21020-10000-02233
Plan Check / Job No.
B21LA18398
Group
Building
Type
Nonbldg-New
Sub-Type
Apartment
Primary Use
(23) Shoring (Temporary)
Work Description
Early Start - Temporary shoring for highrise mixed use building. ( BUILDING UNDER PERMIT 18010-10000-00190)
Permit Issued
Issued on 3/9/2022
Issuing Office
Current Status
Permit Finaled on 4/29/2024

Permit Application Status History

Submitted 9/30/2021 APPLICANT
Assigned to Plan Check Engineer 10/28/2021 SUEN LIEU
Corrections Issued 11/5/2021 SUEN LIEU
Building Plans Picked Up 11/12/2021 APPLICANT
Quality Review Completed 11/18/2021 SAI KHUM
Applicant returned to address corrections 12/1/2021 SUEN LIEU
Applicant returned to address corrections 12/15/2021 SUEN LIEU
Plan Check Approved 3/9/2022 SUEN LIEU
Issued 3/9/2022 APPLICANT
Permit Finaled 4/26/2024 DAVID BURKHEAD

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/27/2022 JEANETTE VONG
Miscellaneous Cleared 1/27/2022 RUBEN VASQUEZ
Stormwater Pollution Mitigatn Cleared 1/27/2022 IDA MEISAMI-FARD
Work Adjacent to Public Way Cleared 2/17/2022 JOSE RODRIGUEZ
Abandoned oil well Cleared 2/22/2022 KURT CORRAL
ZI Cleared 2/24/2022 DAVID URITA
"Q" conditions Cleared 3/7/2022 RUBEN VASQUEZ
"T" removal Cleared 3/7/2022 RUBEN VASQUEZ
CPC Cleared 3/7/2022 RUBEN VASQUEZ
CPC Cleared 3/7/2022 RUBEN VASQUEZ
Metro Rail approval Cleared 3/7/2022 SUEN LIEU
Opn space landscape/Water mgmt Cleared 3/7/2022 RUBEN VASQUEZ
Site Plan review Cleared 3/7/2022 RUBEN VASQUEZ
Tract Map conditions Cleared 3/7/2022 RUBEN VASQUEZ
Address approval Cleared 3/8/2022 WALLIE JONG
Bicycle Parking Cleared 3/8/2022 MSTAFA AL-MSARI
DAS Clearance Cleared 3/8/2022 SUEN LIEU
Encroachment in public way Cleared 3/8/2022 MSTAFA AL-MSARI
Fire Marshall Fire Life Safety Cleared 3/8/2022 MENOA AGHAJANI
Green Code Cleared 3/8/2022 AARON COSTA
Highway dedication Cleared 3/8/2022 WALLIE JONG
Hydrant and Access approval Cleared 3/8/2022 KURT CORRAL
Metro Rail approval Cleared 3/8/2022 SUEN LIEU
Permit Cleared 3/8/2022 WALLIE JONG
Project located in CRA area Cleared 3/8/2022 DAVID URITA
Sewer availability Cleared 3/8/2022 WALLIE JONG
Building over 3-story or 36-ft Cleared 3/9/2022 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 3/9/2022 CALOSHA APPROVED
Low Impact Development Cleared 3/9/2022 IDA MEISAMI-FARD
Roof/Waste drainage to street Cleared 3/9/2022 WALLIE JONG

Contact Information

Contractor A B S Shoring Inc; Lic. No.: 1027825-A 11540 SANTA MONICA BLVD #201      LOS ANGELES, CA 90025
Engineer Funk,, David Lyle; Lic. No.: S5421 319 MAIN STREET      EL SEGUNDO, CA 90245

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/11/2022 Partial Inspection DANIEL MC AULIFFE
Deputy Grading 3/24/2022 Conditional Approval JONATHAN QUACH
Deputy Grading 3/25/2022 Approved SORIN CIRSTOIU
Footing/Foundation/Slab 3/25/2022 Corrections Issued SORIN CIRSTOIU
Deputy Grading 3/29/2022 Approved SORIN CIRSTOIU
Deputy Grading 3/30/2022 Conditional Approval DANIEL MC AULIFFE
Deputy Grading 3/31/2022 Approved SORIN CIRSTOIU
Deputy Grading 4/1/2022 Conditional Approval DANIEL MC AULIFFE
Deputy Grading 4/4/2022 Conditional Approval DANIEL MC AULIFFE
Deputy Grading 4/5/2022 Conditional Approval DANIEL MC AULIFFE
Deputy Grading 4/6/2022 Conditional Approval DANIEL MC AULIFFE
Deputy Grading 4/7/2022 Conditional Approval DANIEL MC AULIFFE
Deputy Grading 4/8/2022 Conditional Approval DANIEL MC AULIFFE
Deputy Grading 4/11/2022 Conditional Approval DANIEL MC AULIFFE
Deputy Grading 4/12/2022 Conditional Approval DANIEL MC AULIFFE
Deputy Grading 4/13/2022 Approved DANIEL MC AULIFFE
Footing/Foundation/Slab 4/13/2022 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Grading 4/14/2022 Conditional Approval DAVID BURKHEAD
Deputy Grading 4/15/2022 Approved DANIEL MC AULIFFE
Deputy Grading 4/18/2022 Conditional Approval DANIEL MC AULIFFE
Deputy Grading 4/19/2022 Approved DANIEL MC AULIFFE
Deputy Grading 4/20/2022 Conditional Approval DANIEL MC AULIFFE
Deputy Grading 4/21/2022 Conditional Approval DANIEL MC AULIFFE
Deputy Grading 4/22/2022 Conditional Approval DANIEL MC AULIFFE
Deputy Steel/Welding 4/22/2022 Conditional Approval DANIEL MC AULIFFE
Deputy Grading 4/25/2022 Conditional Approval DANIEL MC AULIFFE
Deputy Grading 4/26/2022 Conditional Approval DANIEL MC AULIFFE
Deputy Grading 4/27/2022 Conditional Approval DANIEL MC AULIFFE
Deputy Grading 4/28/2022 Approved DANIEL MC AULIFFE
Deputy Grading 4/29/2022 Conditional Approval DAVID BURKHEAD
Piling/Pier/Caisson 4/29/2022 Partial Inspection DAVID BURKHEAD
Deputy Grading 5/2/2022 Conditional Approval DAVID BURKHEAD
Deputy Grading 5/3/2022 Conditional Approval TED RIES
Deputy Grading 5/4/2022 Conditional Approval DAVID BURKHEAD
Deputy Grading 5/5/2022 Conditional Approval TED RIES
Deputy Grading 5/6/2022 Conditional Approval TED RIES
Deputy Grading 5/9/2022 Conditional Approval TED RIES
Deputy Grading 5/10/2022 Approved TED RIES
Deputy Grading 5/11/2022 Conditional Approval TED RIES
Deputy Grading 5/12/2022 Conditional Approval DAVID BURKHEAD
Deputy Grading 5/13/2022 Conditional Approval TED RIES
Deputy Grading 5/16/2022 Conditional Approval TED RIES
Deputy Grading 5/17/2022 Conditional Approval TED RIES
Deputy Grading 5/18/2022 Conditional Approval TED RIES
Deputy Grading 5/19/2022 Conditional Approval TED RIES
Deputy Grading 5/20/2022 Conditional Approval ERNESTO CORRAL
Deputy Grading 5/23/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 5/23/2022 Conditional Approval ERNESTO CORRAL
Deputy Grading 5/24/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 5/24/2022 Conditional Approval ERNESTO CORRAL
Deputy Grading 5/25/2022 Conditional Approval TERRY HERR
Deputy Reinf. Concrete 5/25/2022 Conditional Approval TERRY HERR
Deputy Grading 5/26/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 5/26/2022 Conditional Approval ERNESTO CORRAL
Deputy Grading 5/27/2022 Conditional Approval TED RIES
Deputy Reinf. Concrete 5/27/2022 Conditional Approval TED RIES
Deputy Grading 5/31/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 5/31/2022 Conditional Approval ERNESTO CORRAL
Deputy Grading 6/1/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/1/2022 Conditional Approval ERNESTO CORRAL
Deputy Grading 6/2/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/2/2022 Conditional Approval ERNESTO CORRAL
Deputy Grading 6/3/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/3/2022 Conditional Approval ERNESTO CORRAL
Deputy Grading 6/6/2022 Conditional Approval ERNESTO CORRAL
Deputy Grading 6/7/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/7/2022 Conditional Approval ERNESTO CORRAL
Deputy Grading 6/8/2022 Conditional Approval ERNESTO CORRAL
Deputy Grading 6/9/2022 Conditional Approval ERNESTO CORRAL
Deputy Grading 6/10/2022 Conditional Approval ERNESTO CORRAL
Deputy Grading 5/10/2023 Conditional Approval RAFAEL ESPINOZA
Deputy Grading 7/20/2023 Conditional Approval DAVID BURKHEAD
Deputy Grading 7/21/2023 Conditional Approval RAFAEL ESPINOZA
Final 4/26/2024 Permit Finaled DAVID BURKHEAD