9719 W HEATHER ROAD 90210

Certificate Information: 9719 W HEATHER ROAD 90210

Application / Permit
21020-10000-02123
Plan Check / Job No.
B21LA17495
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
(N) RETAINING WALL, 10' ht. x 104' long. 2 OF 4
Permit Issued
Issued on 4/5/2023
Issuing Office
Valley
Current Status
Permit Finaled on 12/27/2024

Permit Application Status History

Submitted 9/20/2021 APPLICANT
Assigned to Plan Check Engineer 10/7/2021 SAM CHANG
Corrections Issued 10/20/2021 SAM CHANG
Quality Review Completed 10/25/2021 EUGENE BARBEAU
Applicant returned to address corrections 3/1/2022 SAM CHANG
Applicant returned to address corrections 3/18/2022 SAM CHANG
Building Plans Picked Up 3/29/2022 APPLICANT
Applicant returned to address corrections 7/18/2022 SAM CHANG
Plan Check Approved 11/17/2022 SAM CHANG
Issued 4/5/2023 APPLICANT
Permit Finaled 12/26/2024 ALEXANDER HELFER

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/20/2021 SAM CHANG
Landscape for retaining wall Cleared 3/29/2022 RYAN LY
Excavation more than 5-ft deep Cleared 11/17/2022 CALOSHA APPROVED

Contact Information

Contractor Third Generation Construction Inc; Lic. No.: 893694-B 13369 LOS OLIVOS ROAD      SYLMAR, CA 91342
Engineer Koma,, Shahram Javadi; Lic. No.: C69497 23241 VENTURA BLVD 300      WOODLAND HILLS, CA 91364
Geologist Miller,, Jonathan Steven; Lic. No.: EG2391 24736 CALVERT STREET      WOODLAND HILLS, CA 91367

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 5/18/2023 Conditional Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 5/19/2023 Not Ready for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 5/19/2023 Partial Inspection ALEXANDER HELFER
Reinforced Concrete Frame 5/19/2023 Not Ready for Inspection RAUL BARAJAS
Final 12/26/2024 Permit Finaled ALEXANDER HELFER