700 N ALAMEDA ST 90012

Certificate Information: 700 N ALAMEDA ST 90012

Application / Permit
21020-10000-02077
Plan Check / Job No.
B21LA17122
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(23) Fence Wall
Work Description
PERIMETER FENCING & GATE AROUND (E) COURTYARD.
Permit Issued
Issued on 1/26/2023
Issuing Office
Metro
Current Status
Permit Finaled on 8/7/2024

Permit Application Status History

Submitted 9/15/2021 APPLICANT
Assigned to Plan Check Engineer 9/17/2021 TSE MING HUANG
Corrections Issued 9/19/2021 TSE MING HUANG
Applicant returned to address corrections 4/7/2022 TSE MING HUANG
Plan Check Approved 4/19/2022 TSE MING HUANG
Building Plans Picked Up 4/20/2022 APPLICANT
Issued 1/26/2023 APPLICANT
Permit Finaled 8/7/2024 RONALD JIMENEZ

Permit Application Clearance Information

ZA Case Cleared 11/30/2021 RICHARD REASER
ZI Cleared 11/30/2021 RICHARD REASER
City owned building/parcel Cleared 12/2/2021 TSE MING HUANG
Specific Plan Cleared 12/6/2021 YI LU
Metro Rail approval Cleared 12/10/2021 TSE MING HUANG
Specific Plan Cleared 1/19/2022 KEVIN ARUCAN

Contact Information

Architect Atkinson,, Craig Lewis; Lic. No.: C25387 6858 POPPYVIEW DRIVE      OAK PARK, CA 91377
Contractor Caltec Corp; Lic. No.: 852623-B 8732 WESTMINSTER BLVD SUITE #2      WESTMINSTER, CA 92683
Engineer Rich,, Tracy Robert; Lic. No.: S4831 455 CAMINO HERMOSO      SAN MARCOS, CA 92078

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/27/2023 Not Ready for Inspection RAFAEL CORTES
Final 11/8/2023 No Access for Inspection RAMAZANALI ALMASI
Pre-Inspection 11/30/2023 Approved RAFAEL CORTES
Deputy Drilled-In Anchors 12/6/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 12/11/2023 Conditional Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 12/13/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 12/14/2023 Conditional Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 12/18/2023 Conditional Approval RAMAZANALI ALMASI
Footing/Foundation/Slab 12/19/2023 Partial Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 12/20/2023 Conditional Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 12/21/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 12/29/2023 Conditional Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 1/2/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 1/2/2024 Conditional Approval RAMAZANALI ALMASI
Footing/Foundation/Slab 1/2/2024 Partial Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 1/3/2024 No Access for Inspection MICHAEL ROSENBERG
Deputy Drilled-In Anchors 1/4/2024 Conditional Approval RAMAZANALI ALMASI
Footing/Foundation/Slab 1/4/2024 Partial Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 1/5/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 1/10/2024 Partial Approval MARTIN TAVITIAN
Deputy Reinf. Concrete 1/10/2024 Partial Approval MARTIN TAVITIAN
Footing/Foundation/Slab 1/10/2024 Partial Approval MARTIN TAVITIAN
Deputy Drilled-In Anchors 1/12/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 1/12/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 1/16/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 1/16/2024 Conditional Approval RAMAZANALI ALMASI
Footing/Foundation/Slab 1/16/2024 Partial Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 1/17/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 1/17/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 1/18/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 1/18/2024 Conditional Approval RAMAZANALI ALMASI
Footing/Foundation/Slab 1/18/2024 Partial Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 1/24/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 1/24/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 1/26/2024 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 1/26/2024 Conditional Approval LARRY ARNICK
Footing/Foundation/Slab 1/26/2024 Partial Approval LARRY ARNICK
Deputy Drilled-In Anchors 1/29/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 1/29/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 2/8/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Other (see comments) 2/8/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 2/8/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 2/14/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 2/14/2024 Conditional Approval RAMAZANALI ALMASI
Footing/Foundation/Slab 2/14/2024 Partial Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 2/15/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 2/15/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 2/16/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 2/16/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 2/27/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 2/27/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 2/28/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 2/28/2024 Conditional Approval RAMAZANALI ALMASI
Footing/Foundation/Slab 2/28/2024 Partial Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 3/1/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 3/1/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 3/8/2024 Conditional Approval RONALD JIMENEZ
Deputy Reinf. Concrete 3/8/2024 Conditional Approval RONALD JIMENEZ
Footing/Foundation/Slab 3/8/2024 Partial Approval RONALD JIMENEZ
Deputy Drilled-In Anchors 3/13/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 3/13/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 3/15/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 3/15/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 3/18/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 3/18/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 3/19/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 3/19/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 3/20/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 3/20/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 3/21/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 3/21/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 3/22/2024 Conditional Approval RONALD JIMENEZ
Deputy Reinf. Concrete 3/22/2024 Conditional Approval RONALD JIMENEZ
Footing/Foundation/Slab 3/22/2024 Partial Approval RONALD JIMENEZ
Deputy Drilled-In Anchors 3/26/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 3/26/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 4/3/2024 Conditional Approval RONALD JIMENEZ
Deputy Reinf. Concrete 4/3/2024 Conditional Approval RONALD JIMENEZ
Deputy Drilled-In Anchors 4/5/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 4/5/2024 Conditional Approval RAMAZANALI ALMASI
Footing/Foundation/Slab 4/5/2024 Partial Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 4/10/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 4/10/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 4/11/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 4/11/2024 Conditional Approval RAMAZANALI ALMASI
Footing/Foundation/Slab 4/11/2024 Partial Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 4/12/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 4/12/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 4/16/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 4/16/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 4/17/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 4/17/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 4/18/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 4/18/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Other (see comments) 4/22/2024 Conditional Approval RONALD JIMENEZ
Footing/Foundation/Slab 4/22/2024 Partial Approval RONALD JIMENEZ
Deputy Other (see comments) 4/30/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Other (see comments) 5/1/2024 Conditional Approval RAMAZANALI ALMASI
Footing/Foundation/Slab 5/1/2024 Not Ready for Inspection RAMAZANALI ALMASI
Deputy Other (see comments) 5/2/2024 Conditional Approval RAMAZANALI ALMASI
Footing/Foundation/Slab 5/2/2024 Partial Approval RAMAZANALI ALMASI
Deputy Other (see comments) 5/3/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 5/6/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 5/6/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Other (see comments) 5/17/2024 Conditional Approval RONALD JIMENEZ
Deputy Other (see comments) 5/20/2024 Conditional Approval RAMAZANALI ALMASI
Footing/Foundation/Slab 5/24/2024 Partial Approval RAMAZANALI ALMASI
Deputy Other (see comments) 6/3/2024 No Access for Inspection MICHAEL ROSENBERG
Footing/Foundation/Slab 6/3/2024 Not Ready for Inspection RONALD JIMENEZ
Deputy Other (see comments) 6/4/2024 Conditional Approval RONALD JIMENEZ
Footing/Foundation/Slab 6/4/2024 Partial Approval RONALD JIMENEZ
Deputy Other (see comments) 6/7/2024 Conditional Approval RONALD JIMENEZ
Footing/Foundation/Slab 6/7/2024 Partial Approval RONALD JIMENEZ
Deputy Reinf. Concrete 6/12/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 7/2/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 7/2/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 7/3/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 7/3/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 7/10/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 7/11/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 7/12/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 7/17/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 7/17/2024 Conditional Approval RAMAZANALI ALMASI
Final 7/31/2024 Conditional Approval RONALD JIMENEZ
Final 8/5/2024 Not Ready for Inspection RAMAZANALI ALMASI
Final 8/7/2024 Permit Finaled RONALD JIMENEZ