549 S HARVARD BLVD 90020

Certificate Information: 549 S HARVARD BLVD 90020

Application / Permit
21020-10000-01970
Plan Check / Job No.
B21LA16308
Group
Building
Type
Nonbldg-New
Sub-Type
Apartment
Primary Use
(23) Shoring (Temporary)
Work Description
TEMPORARY SHORING PLAN CHECK FOR NEW 7 STORY 150 UNITS (15 ELI = 10%) MIXED USE AFFORDABLE HOUSING APARTMENT TO INCLUDE 5 STORY TYPE IIIA APARTMENT OVER 2 STORY TYPE IA RESIDENTIAL / PARKING / RETAIL OVER 2 LEVEL SUBTERRANEAN PARKING, TIER 3 TOC WITH ADDITIONAL INCENTIVES. BUILDING PERMIT 20010-10000-04305
Permit Issued
Issued on 6/1/2023
Issuing Office
Metro
Current Status
Permit Finaled on 9/6/2025

Permit Application Status History

Submitted 9/1/2021 APPLICANT
Assigned to Plan Check Engineer 9/16/2021 VU NGUYEN
Corrections Issued 9/21/2021 VU NGUYEN
Quality Review Completed 9/22/2021 EUGENE BARBEAU
Building Plans Picked Up 9/24/2021 APPLICANT
Applicant returned to address corrections 12/16/2021 VU NGUYEN
Plan Check Approved 6/14/2022 VU NGUYEN
Issued 6/1/2023 APPLICANT
Permit Finaled 9/5/2025 DAVID BURKHEAD

Permit Application Clearance Information

CPC Cleared 11/19/2021 RUBEN VASQUEZ
Miscellaneous Cleared 11/19/2021 RUBEN VASQUEZ
Miscellaneous Cleared 11/19/2021 RUBEN VASQUEZ
Miscellaneous Cleared 11/19/2021 RUBEN VASQUEZ
Miscellaneous Cleared 11/19/2021 RUBEN VASQUEZ
Encroachment in public way Cleared 1/10/2022 JEREMY CHOK
Eng Process Fee Ord 176,300 Cleared 1/11/2022 JEREMY CHOK
Excavation more than 5-ft deep Cleared 1/25/2022 CALOSHA APPROVED
Work Adjacent to Public Way Cleared 3/25/2022 ARMEN SARKISIAN

Contact Information

Contractor Wilshire Construction L P; Lic. No.: 1048091-B 3470 WILSHIRE STE 500      LOS ANGELES, CA 90010
Engineer Funk,, David Lyle; Lic. No.: S5421 319 MAIN STREET      EL SEGUNDO, CA 90245
Engineer Tang,, Stanley Siu Kei; Lic. No.: C56178 1105 N AVON STREET      BURBANK, CA 91505

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/8/2023 Approved DAVID BURKHEAD
Deputy Grading 6/21/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 6/21/2023 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 6/22/2023 Partial Inspection TIMOTHY POWELL
Deputy Grading 6/27/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 6/27/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 6/28/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 6/28/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 6/29/2023 Conditional Approval RAFAEL ESPINOZA
Deputy Grading 7/10/2023 Conditional Approval TED RIES
Deputy Grading 7/18/2023 Approved DAVID BURKHEAD
Deputy Reinf. Concrete 7/18/2023 Approved DAVID BURKHEAD
Piling/Pier/Caisson 7/26/2023 Partial Inspection RAFAEL CORTES
Special/Order Compliance 7/26/2023 Approved RONALD JIMENEZ
Piling/Pier/Caisson 8/4/2023 Partial Approval TED RIES
Piling/Pier/Caisson 8/15/2023 Partial Inspection GREGORY POMISH
Piling/Pier/Caisson 8/29/2023 Partial Inspection VAHE KELEDJIAN
Deputy Grading 9/18/2023 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 4/23/2024 Not Ready for Inspection DAVID BURKHEAD
Final 9/5/2025 Permit Finaled DAVID BURKHEAD