2301 W 3RD ST 90057
Certificate Information: 2301 W 3RD ST 90057
- Application / Permit
- 21020-10000-01880
- Plan Check / Job No.
- B21LA15782
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (61) Use of Land
- Work Description
- USE OF LAND FOR 55 EMERGENCY SLEEPING CABINS (107 BEDS TOTAL) PER CBC APPENDIX O AND GOVERNMENT CODE SECTION 8698, et seq, ADMIN BUILDING, 1 GUARD BOOTH, AND 2 HYGIENE TRAILERS. A BRIDGE HOME.
- Permit Issued
- Issued on 9/22/2021
- Issuing Office
- Current Status
- CofO Issued on 12/16/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2021 | KEVIN MORALES |
| Corrections Issued | 9/4/2021 | KEVIN MORALES |
| Quality Review Completed | 9/7/2021 | EUGENE BARBEAU |
| Applicant returned to address corrections | 9/14/2021 | KEVIN MORALES |
| Plan Check Approved | 9/22/2021 | KEVIN MORALES |
| Issued | 9/22/2021 | APPLICANT |
| Building Plans Picked Up | 9/23/2021 | APPLICANT |
| CofO in Progress | 12/16/2021 | ERNESTO CORRAL |
| CofO Issued | 12/16/2021 | ERNESTO CORRAL |
| Permit Finaled | 12/16/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 8/25/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 8/25/2021 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 8/25/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 9/13/2021 | RENZ SORIANO |
| Grading Pre-Inspection | Cleared | 9/14/2021 | ROBERT HUGHES |
| Hydrant and Access approval | Cleared | 9/14/2021 | KURT CORRAL |
| DAS Clearance | Cleared | 9/16/2021 | EUGENE BARBEAU |
Contact Information
| Contractor | Ford E C Inc; Lic. No.: 396212-B | 10850 WILSHIRE BLVD #380 LOS ANGELES, CA 90024 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/8/2021 | Partial Approval | TIMOTHY BUXTON |
| Special/Order Compliance | 10/19/2021 | Approved | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 10/20/2021 | Partial Approval | TIMOTHY BUXTON |
| Final | 12/7/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Pre-Inspection | 12/14/2021 | Not Ready for Inspection | NICK DANERI |
| Deputy Drilled-In Anchors | 12/15/2021 | Conditional Approval | JONATHAN QUACH |
| Final | 12/15/2021 | Conditional Approval | NICK DANERI |