6320 E GARVANZA AVE 90042
Certificate Information: 6320 E GARVANZA AVE 90042
- Application / Permit
- 21020-10000-01849
- Plan Check / Job No.
- B21LA15588
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- Shoring for a subterranean parking construction
- Permit Issued
- Issued on 5/5/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 2/26/2026
Permit Application Status History
| Submitted | 8/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2021 | VU NGUYEN |
| Corrections Issued | 9/16/2021 | VU NGUYEN |
| Quality Review Completed | 9/20/2021 | EUGENE BARBEAU |
| Green Plans Picked Up | 9/21/2021 | APPLICANT |
| Building Plans Picked Up | 9/22/2021 | APPLICANT |
| Applicant returned to address corrections | 9/12/2022 | VU NGUYEN |
| Applicant returned to address corrections | 3/29/2023 | VU NGUYEN |
| Plan Check Approved | 5/5/2023 | VU NGUYEN |
| Issued | 5/5/2023 | APPLICANT |
| Permit Finaled | 2/26/2026 | RONALD JIMENEZ |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/5/2021 | CECILIO NAVARRO |
| "Q" conditions | Cleared | 3/21/2023 | RYAN LY |
| CPC | Cleared | 3/21/2023 | RYAN LY |
| Miscellaneous | Cleared | 3/21/2023 | RYAN LY |
| Miscellaneous | Cleared | 3/21/2023 | RYAN LY |
| Miscellaneous | Cleared | 3/21/2023 | RYAN LY |
| Miscellaneous | Cleared | 3/21/2023 | RYAN LY |
| Work Adjacent to Public Way | Cleared | 4/3/2023 | LARRY LEE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Berkoz,, Ertunga; Lic. No.: S2504 | 4665 ELLENITA AVE TARZANA, CA 91356 |
Inspector Information
| RONALD JIMENEZ, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| LARRY ARNICK, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEY BUCHANAN, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| ERNESTO CORRAL, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL ESPINOZA, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 5/9/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Pre-Inspection | 5/9/2023 | Corrections Issued | LARRY ARNICK |
| Deputy Reinf. Concrete | 5/11/2023 | Approved | LARRY ARNICK |
| Piling/Pier/Caisson | 5/11/2023 | Conditional Approval | LARRY ARNICK |
| Deputy Grading | 5/12/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 5/12/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/15/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 5/15/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/16/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 5/16/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/17/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 5/17/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/18/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 5/18/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/19/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 5/19/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/22/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 5/22/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/30/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 5/30/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Excavation/Setback/Form/Re-Bar | 6/7/2023 | Partial Inspection | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 6/22/2023 | Partial Approval | RAMAZANALI ALMASI |
| Deputy Shotcrete | 6/23/2023 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Shotcrete | 6/28/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 7/6/2023 | Conditional Approval | LARRY ARNICK |
| Deputy Reinf. Concrete | 7/10/2023 | Conditional Approval | LARRY ARNICK |
| Deputy Reinf. Concrete | 7/12/2023 | Conditional Approval | LARRY ARNICK |
| Final | 2/26/2026 | Permit Finaled | RONALD JIMENEZ |