133 S MESA ST 1-4 90731
Certificate Information: 133 S MESA ST 1-4 90731
- Application / Permit
- 21020-10000-01827
- Plan Check / Job No.
- B21LA15394
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Apartment
- Primary Use
- (23) Retaining Wall
- Work Description
- INSTALL (N) CONCRETE RETAINING WALL AT REAR OF HOUSE TO REPLACE (E) RETAINING WALL. 1 OF 3
- Permit Issued
- Issued on 3/23/2022
- Issuing Office
- Current Status
- Permit Finaled on 3/29/2023
Permit Application Status History
| Submitted | 8/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 9/9/2021 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 9/9/2021 | SAI KHUM |
| Applicant returned to address corrections | 1/12/2022 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 1/13/2022 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 2/24/2022 | FARSHAD ALIMOHAMADI |
| Issued | 3/23/2022 | APPLICANT |
| Building Plans Picked Up | 3/25/2022 | APPLICANT |
| Permit Finaled | 3/29/2023 | JOEY BUCHANAN |
Permit Application Clearance Information
| "Q" conditions | Cleared | 9/28/2021 | RICHARD REASER |
| Community Plan Implem. Overlay | Cleared | 9/28/2021 | RICHARD REASER |
| Work Adjacent to Public Way | Cleared | 9/28/2021 | ERIK BEASLEY |
| Historic Resource Verification | Cleared | 9/29/2021 | MICAELA TORRES-GIL |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2021 | ERIK BEASLEY |
| Redevelopment Project Area | Cleared | 11/23/2021 | DAVID URITA |
| Tenant Habitability Plan | Cleared | 12/13/2021 | ISMAEL HERNANDEZ |
| Grading Pre-Inspection | Cleared | 2/24/2022 | SAI KHUM |
Contact Information
| Contractor | Alpha Structural Inc; Lic. No.: 663409-B | 8334 FOOTHILL BLVD SUNLAND, CA 91040 |
| Engineer | Demers,, Joe Alan; Lic. No.: C71535 | 894 SANTA MARIA CIRCLE DUARTE, CA 91010 |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 4/26/2022 | Approved | JOEY BUCHANAN |
| Deputy Other (see comments) | 4/26/2022 | Approved | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 5/9/2022 | Approved | JOEY BUCHANAN |
| Deputy Other (see comments) | 5/16/2022 | Approved | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 5/16/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Final | 11/29/2022 | Conditional Approval | JOEY BUCHANAN |
| Final | 3/29/2023 | Permit Finaled | JOEY BUCHANAN |