6710 W HOLLYWOOD BLVD 90028
Certificate Information: 6710 W HOLLYWOOD BLVD 90028
- Application / Permit
- 21020-10000-01796
- Plan Check / Job No.
- B21LA15156
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- TEMPORARY SHORING FOR SUPPORT OF EXCAVATION TO CONSTRUCT NEW CONCRETE FOUNDATIONS PER 21016-10000-02583
- Permit Issued
- Issued on 2/17/2022
- Issuing Office
- Current Status
- Permit Finaled on 7/20/2023
Permit Application Status History
| Submitted | 8/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2021 | SUEN LIEU |
| Corrections Issued | 9/16/2021 | SUEN LIEU |
| Quality Review Completed | 9/21/2021 | SAI KHUM |
| Applicant returned to address corrections | 12/16/2021 | SUEN LIEU |
| Applicant returned to address corrections | 1/10/2022 | SUEN LIEU |
| Applicant returned to address corrections | 1/21/2022 | SUEN LIEU |
| Plan Check Approved | 2/17/2022 | SUEN LIEU |
| Issued | 2/17/2022 | APPLICANT |
| Permit Finaled | 7/19/2023 | RONALD JIMENEZ |
Permit Application Clearance Information
| City Hist. Cultural Monument | Cleared | 1/24/2022 | LAMBERT GIESSINGER |
| Historic Resource Verification | Cleared | 1/24/2022 | LAMBERT GIESSINGER |
| Historic monument | Cleared | 1/24/2022 | LAMBERT GIESSINGER |
| ZI | Cleared | 2/1/2022 | DAVID URITA |
| Stormwater Pollution Mitigatn | Cleared | 2/7/2022 | AMMAR ELTAWIL |
| Excavation more than 5-ft deep | Cleared | 2/11/2022 | CALOSHA APPROVED |
| Metro Rail approval | Cleared | 2/15/2022 | SUEN LIEU |
Contact Information
| Contractor | The Whiting-Turner Contracting Company; Lic. No.: 311107-B | 800 R STREET SACRAMENTO, CA 95811 |
| Engineer | Cefali,, David Allen; Lic. No.: S3658 | 4344 LAUREL CANYON BLVD_STE 3 STUDIO CITY, CA 91604 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/18/2023 | Approved | RONALD JIMENEZ |
| Grading Pre-Inspection | 7/18/2023 | Approved | RONALD JIMENEZ |
| Excavation/Setback/Form/Re-Bar | 7/19/2023 | Approved | RONALD JIMENEZ |
| Final | 7/19/2023 | Permit Finaled | RONALD JIMENEZ |
| Grading Pre-Inspection | 7/19/2023 | Approved | RONALD JIMENEZ |
| Piling/Pier/Caisson | 7/19/2023 | Approved | RONALD JIMENEZ |