4411 N CONCHITA WAY 91356

Certificate Information: 4411 N CONCHITA WAY 91356

Application / Permit
21020-10000-01714
Plan Check / Job No.
B21LA14525
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
NEW 160 ' LONG WITH MAX 10' IN HEIGHT, 2 FREE STANDING SITE RETAINING WALLS AT REAR OF THE PROPERTY .
Permit Issued
Issued on 3/23/2023
Issuing Office
Current Status
Permit Finaled on 2/13/2025

Permit Application Status History

Submitted 8/3/2021 APPLICANT
Assigned to Plan Check Engineer 9/2/2021 GARO TELMI
Corrections Issued 9/15/2021 GARO TELMI
Quality Review Completed 9/21/2021 KEN GILL
Building Plans Picked Up 9/23/2021 APPLICANT
Applicant returned to address corrections 1/19/2022 GARO TELMI
Applicant returned to address corrections 2/2/2023 GARO TELMI
Applicant returned to address corrections 3/8/2023 GARO TELMI
Plan Check Approved 3/22/2023 GARO TELMI
Issued 3/23/2023 APPLICANT
Permit Finaled 2/13/2025 ROBERT PINA

Permit Application Clearance Information

Low Impact Development Cleared 9/22/2022 DEBORA LEITE
Miscellaneous Cleared 9/28/2022 NELSON RODRIGUEZ
Roof/Waste drainage to street Cleared 12/29/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/30/2023 CARLOS AGUILERA
Excavation more than 5-ft deep Cleared 2/2/2023 CALOSHA APPROVED
Grading Pre-Inspection Cleared 2/2/2023 LANNY MERRICK
Landscape for retaining wall Cleared 3/16/2023 MAXFIELD VERMY

Contact Information

Contractor Owner-Builder       ,
Engineer Alrayes,, Nidham Aram; Lic. No.: C65487 10346 SAMOA AVE      TUJUNGA, CA 91042
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

MANUEL TEJADA, (818) 374-4339 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Reinforced Concrete Frame 6/2/2023 Approved ROBERT PINA
Reinforced Masonry Frame 6/8/2023 Partial Approval ROBERT PINA
Footing/Foundation/Slab 6/15/2023 Not Ready for Inspection ROBERT PINA
Footing/Foundation/Slab 6/16/2023 Partial Approval ROBERT PINA
Footing/Foundation/Slab 6/20/2023 Partial Approval ROBERT PINA
Drywall Nailing 6/28/2023 Partial Approval ROBERT PINA
Floor/Roof Diaphrgm/Shear Wall 6/28/2023 Partial Approval ROBERT PINA
Footing/Foundation/Slab 6/28/2023 Partial Approval ROBERT PINA
Reinforced Concrete Frame 6/28/2023 Partial Approval ROBERT PINA
Reinforced Masonry Frame 6/28/2023 Partial Approval ROBERT PINA
Footing/Foundation/Slab 7/17/2023 Approved ROBERT PINA
Footing/Foundation/Slab 7/18/2023 Partial Approval ROBERT PINA
Reinforced Masonry Frame 7/25/2023 Partial Approval ROBERT PINA
Reinforced Masonry Frame 7/26/2023 Partial Approval BRIAN MILLER
Excavation/Setback/Form/Re-Bar 8/4/2023 Approved MANUEL TEJADA
Reinforced Masonry Frame 8/10/2023 Partial Approval ROBERT PINA
Footing/Foundation/Slab 8/22/2023 Corrections Issued MANUEL TEJADA
Footing/Foundation/Slab 8/24/2023 Approved ROBERT PINA
Reinforced Masonry Frame 8/28/2023 Approved ROBERT PINA
Pre-Inspection 10/13/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 10/17/2023 Not Ready for Inspection ROBERT PINA
Footing/Foundation/Slab 10/20/2023 Approved ROBERT PINA
Final 2/13/2025 Permit Finaled ROBERT PINA