972 S ARAPAHOE ST 90006

Certificate Information: 972 S ARAPAHOE ST 90006

Application / Permit
21020-10000-01680
Plan Check / Job No.
B21LA14129
Group
Building
Type
Nonbldg-New
Sub-Type
Apartment
Primary Use
(23) Shoring (Temporary)
Work Description
TEMPORARY SHORING FOR NEW 5 STORY 12 UNIT AFFORDABLE HOUSING APARTMENT TO INCLUDE 4 STORY TYPE IIIA APARTMENT OVER 1 STORY TYPE IA APARTMENT/ GARAGE
Permit Issued
Issued on 4/26/2023
Issuing Office
Metro
Current Status
Issued on 4/26/2023

Permit Application Status History

Submitted 7/28/2021 APPLICANT
Assigned to Plan Check Engineer 7/29/2021 HERNAN ARREOLA
Corrections Issued 8/3/2021 HERNAN ARREOLA
Quality Review Completed 8/4/2021 JASON HEALEY
Building Plans Picked Up 8/9/2021 APPLICANT
Applicant returned to address corrections 11/18/2021 HERNAN ARREOLA
Plan Check Approved 4/26/2023 HERNAN ARREOLA
Issued 4/26/2023 APPLICANT

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Burrell Builders; Lic. No.: 1009680-B 440 E HUNTINGTON DRIVE STE 300      ARCADIA, CA 91006

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 4/28/2023 Partial Inspection NICK DANERI
Deputy Reinf. Concrete 5/1/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 5/2/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/2/2023 Conditional Approval MICHAEL ROSENBERG
Piling/Pier/Caisson 5/4/2023 Partial Inspection EDWIN GREGORYONA
Deputy Grading 5/8/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 5/9/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/11/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 5/31/2023 Conditional Approval MICHAEL ROSENBERG
Piling/Pier/Caisson 6/5/2023 Partial Inspection NICK DANERI
Piling/Pier/Caisson 6/14/2023 Partial Approval NICK DANERI
Deputy Grading 6/21/2023 Conditional Approval NICK DANERI
Grading Pre-Inspection 6/21/2023 Not Ready for Inspection NICK DANERI
Deputy Grading 7/5/2023 Conditional Approval GREGORY POMISH
Deputy Grading 7/10/2023 Conditional Approval GREGORY POMISH
Reinforced Masonry Frame 7/10/2023 Partial Inspection GREGORY POMISH
Grading Pre-Inspection 8/14/2023 Conditional Approval NICK DANERI
Grading Pre-Inspection 8/29/2023 Conditional Approval NICK DANERI
Pre-Inspection 9/18/2023 Partial Inspection GREGORY POMISH
Footing/Foundation/Slab 9/27/2023 Not Ready for Inspection GREGORY POMISH
Reinforced Masonry Frame 10/13/2023 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 10/16/2023 Partial Approval GREGORY POMISH
Reinforced Masonry Frame 10/16/2023 Partial Inspection GREGORY POMISH
Deputy Shotcrete 10/18/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 10/25/2023 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 10/25/2023 Partial Approval GREGORY POMISH
Deputy Shotcrete 10/30/2023 Conditional Approval NICK DANERI
Light Gage Steel Frame 10/30/2023 Partial Inspection NICK DANERI
Reinforced Concrete Frame 10/30/2023 Partial Approval NICK DANERI
Deputy Reinf. Masonry 11/8/2023 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 11/9/2023 Conditional Approval LARRY ARNICK
Footing/Foundation/Slab 11/9/2023 Approved LARRY ARNICK
Deputy Reinf. Masonry 11/13/2023 Conditional Approval NICK DANERI
Footing/Foundation/Slab 11/13/2023 Partial Approval NICK DANERI
Reinforced Concrete Frame 11/14/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Masonry 11/15/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 11/20/2023 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 11/21/2023 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 11/28/2023 Conditional Approval GREGORY POMISH
Reinforced Concrete Frame 11/30/2023 Partial Approval NICK DANERI
Reinforced Masonry Frame 11/30/2023 Partial Approval NICK DANERI
Reinforced Masonry Frame 12/14/2023 Partial Approval NICK DANERI
Footing/Foundation/Slab 1/10/2024 Partial Approval GREGORY POMISH
Footing/Foundation/Slab 2/8/2024 Partial Approval GREGORY POMISH
Reinforced Concrete Frame 2/8/2024 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 3/4/2024 Not Ready for Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 3/5/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 3/19/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 3/21/2024 Partial Approval NICK DANERI
Drywall Nailing 3/29/2024 Partial Approval NICK DANERI
Insulation 3/29/2024 Partial Approval NICK DANERI
Deputy Wood Construction 5/21/2024 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 5/21/2024 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 5/24/2024 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 5/24/2024 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 6/7/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 6/28/2024 Not Ready for Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 7/1/2024 Partial Approval NICK DANERI
Wood Frame 7/18/2024 Partial Approval EDWIN GREGORYONA
Wood Frame 7/19/2024 Partial Inspection NICK DANERI
Drywall Nailing 9/26/2024 Partial Approval JEROME BLACKWOOD
Drywall Nailing 10/11/2024 Partial Approval PAUL BAZERKANIAN