4859 S CRENSHAW BLVD 90043
Certificate Information: 4859 S CRENSHAW BLVD 90043
- Application / Permit
- 21020-10000-01594
- Plan Check / Job No.
- B21LA13383
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (61) Use of Land
- Work Description
- NEW GREASE INTERCEPTOR.
- Permit Issued
- Issued on 2/23/2022
- Issuing Office
- Current Status
- CofO Issued on 1/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/19/2021 | TSE MING HUANG |
| Corrections Issued | 7/22/2021 | TSE MING HUANG |
| Building Plans Picked Up | 7/27/2021 | APPLICANT |
| Applicant returned to address corrections | 12/2/2021 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 1/26/2022 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 2/1/2022 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 2/2/2022 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 2/3/2022 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 2/4/2022 | SALVADOR QUINTANILLA |
| Plan Check Approved | 2/22/2022 | SALVADOR QUINTANILLA |
| Issued | 2/23/2022 | APPLICANT |
| CofO in Progress | 1/16/2024 | ERNESTO CORRAL |
| Permit Finaled | 1/16/2024 | ERNESTO CORRAL |
| CofO Issued | 1/16/2024 | ERNESTO CORRAL |
| Permit Finaled | 1/16/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Specific Plan | Cleared | 7/27/2021 | KYLE WINSTON |
| Miscellaneous | Cleared | 7/30/2021 | DAVID URITA |
| Miscellaneous | Cleared | 7/30/2021 | DAVID URITA |
| Redevelopment Project Area | Cleared | 7/30/2021 | DAVID URITA |
| Roof/Waste drainage to street | Cleared | 7/31/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2021 | WALLIE JONG |
| CPC | Cleared | 8/11/2021 | ANACANY HURTADO |
| ZA Case | Cleared | 8/11/2021 | ANACANY HURTADO |
| Encroachment in public way | Cleared | 10/4/2021 | JEREMY CHOK |
| Metro Rail approval | Cleared | 10/5/2021 | TSE MING HUANG |
| Construction near power lines | Cleared | 11/13/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 11/13/2021 | RIDWAN HARDY |
| Work Adjacent to Public Way | Cleared | 1/27/2022 | ARMEN SARKISIAN |
Contact Information
| Contractor | F L Brother'S Construction; Lic. No.: 763054-B | 14525 SOUTH WESTERN AVENUE GARDENA, CA 90249 |
| Engineer | Abedian,, Vanik; Lic. No.: S5323 | 2906 JOLLEY DR BURBANK, CA 91504 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 12/21/2023 | Conditional Approval | MARTIN TAVITIAN |
| Final | 1/4/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Final | 1/16/2024 | OK to Issue CofO | LUIS CCAMACHO |