201 N CARMELINA AVE 90049

Certificate Information: 201 N CARMELINA AVE 90049

Application / Permit
21020-10000-01587
Plan Check / Job No.
B21LA13330
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
(N) UNDERGROUND POOL EQUIPMENT AND GENERATOR VAULT. APPROXIMATELY 32' X 8' 4 OF 6
Permit Issued
Issued on 3/3/2022
Issuing Office
Current Status
CofO Issued on 12/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2021 APPLICANT
Assigned to Plan Check Engineer 8/12/2021 SALVADOR QUINTANILLA
Corrections Issued 9/7/2021 SALVADOR QUINTANILLA
Quality Review Completed 9/10/2021 PETER KIM
Applicant returned to address corrections 9/30/2021 SALVADOR QUINTANILLA
Applicant returned to address corrections 10/21/2021 SALVADOR QUINTANILLA
Applicant returned to address corrections 12/15/2021 SALVADOR QUINTANILLA
Applicant returned to address corrections 12/16/2021 SALVADOR QUINTANILLA
Plan Check Approved 12/20/2021 SALVADOR QUINTANILLA
Issued 3/3/2022 APPLICANT
Building Plans Picked Up 3/9/2022 APPLICANT
CofO in Progress 11/22/2024 KEVIN SARGSYAN
Permit Finaled 12/3/2024 RICHARD STEINBACH
CofO Issued 12/3/2024 RICHARD STEINBACH
Permit Finaled 12/3/2024 RICHARD STEINBACH

Permit Application Clearance Information

ZA Case Cleared 9/16/2021 LOUIS ORTEGA
ZA Case Cleared 9/16/2021 LOUIS ORTEGA

Contact Information

Contractor Tyler Development Corporation; Lic. No.: 451882-B 1932 COTNER AVE      LOS ANGELES, CA 90025
Engineer Hollingsworth,, Robert Alan; Lic. No.: GE2022 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362
Engineer Labib,, Youhanna T.; Lic. No.: S4549 319 MAIN STREET      EL SEGUNDO, CA 90245
Engineer Norton,, Steven A; Lic. No.: C90654 1417 ARMACOST AVENUE      LOS ANGELES, CA 90025

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/14/2022 Partial Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 11/16/2022 Not Ready for Inspection JUAN VALENZUELA
Footing/Foundation/Slab 11/16/2022 Not Ready for Inspection JUAN VALENZUELA
Deputy Reinf. Concrete 11/18/2022 Conditional Approval JUAN VALENZUELA
Final 11/22/2024 OK to Issue CofO KEVIN SARGSYAN