5235-5237 W JEFFERSON BLVD 90016
Certificate Information: 5235-5237 W JEFFERSON BLVD 90016
- Application / Permit
- 21020-10000-01539
- Plan Check / Job No.
- B21LA12955
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- SHORING- PROPOSED PILES FOR TEMP. SHORING FOR BASMENT GARAGE WALLS 2 OF 3
- Permit Issued
- Issued on 4/26/2022
- Issuing Office
- Current Status
- Permit Finaled on 3/16/2023
Permit Application Status History
| Submitted | 7/12/2021 | APPLICANT |
| Green Plans Picked Up | 7/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2021 | SAM CHANG |
| Corrections Issued | 8/16/2021 | SAM CHANG |
| Quality Review Completed | 8/20/2021 | EUGENE BARBEAU |
| Building Plans Picked Up | 8/23/2021 | APPLICANT |
| Applicant returned to address corrections | 10/28/2021 | SAM CHANG |
| Applicant returned to address corrections | 11/10/2021 | SAM CHANG |
| Disabled Access Plans Picked Up | 3/25/2022 | APPLICANT |
| Applicant returned to address corrections | 4/20/2022 | SAM CHANG |
| Plan Check Approved | 4/22/2022 | SAM CHANG |
| Issued | 4/26/2022 | APPLICANT |
| Permit Finaled | 3/15/2023 | EDWIN GREGORYONA |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2021 | RENZ SORIANO |
| Stormwater Pollution Mitigatn | Cleared | 12/14/2021 | MARTIN FRAGOSO |
| Encroachment in public way | Cleared | 4/12/2022 | JEREMY CHOK |
| Work Adjacent to Public Way | Cleared | 4/12/2022 | JOSE RODRIGUEZ |
| Excavation more than 5-ft deep | Cleared | 4/20/2022 | CALOSHA APPROVED |
Contact Information
| Contractor | Calex Engineering Company; Lic. No.: 1035841-A | 23651 PINE STREET NEWHALL, CA 91321 |
| Engineer | Cefali,, David Allen; Lic. No.: S3658 | 4344 LAUREL CANYON BLVD_STE 3 STUDIO CITY, CA 91604 |
| Engineer | Varela,, Gregorio; Lic. No.: C81201 | 1108 S ADAMS ST GLENDALE, CA 91205 |
Inspector Information
| MARTIN TAVITIAN, (213) 482-7357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/3/2022 | Partial Inspection | EDWIN GREGORYONA |
| Piling/Pier/Caisson | 5/3/2022 | Partial Inspection | EDWIN GREGORYONA |
| Pre-Inspection | 5/3/2022 | Partial Inspection | EDWIN GREGORYONA |
| Excavation/Setback/Form/Re-Bar | 5/12/2022 | Partial Approval | EDWIN GREGORYONA |
| Piling/Pier/Caisson | 5/12/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 5/16/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 5/17/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 5/18/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 5/19/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 5/20/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 5/20/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Steel/Welding | 5/20/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 5/23/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 5/25/2022 | Conditional Approval | TERRY HERR |
| Deputy Reinf. Concrete | 5/26/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 6/3/2022 | Conditional Approval | ERNESTO CORRAL |
| Excavation/Setback/Form/Re-Bar | 6/30/2022 | Partial Inspection | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 6/30/2022 | Partial Inspection | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 8/10/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 11/30/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 11/30/2022 | Partial Approval | JAMES POWERS |
| Deputy Grading | 12/1/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 12/2/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 12/5/2022 | Partial Approval | JAMES POWERS |
| Deputy Grading | 12/6/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 12/7/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 12/8/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 12/9/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Final | 3/15/2023 | Permit Finaled | EDWIN GREGORYONA |