7900 S LOYOLA BLVD 90045
Certificate Information: 7900 S LOYOLA BLVD 90045
- Application / Permit
- 21020-10000-01455
- Plan Check / Job No.
- B21LA12433
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- INSTALL 6 LIGHT POLES AT ATHLETIC FIELD
- Permit Issued
- Issued on 11/15/2021
- Issuing Office
- Current Status
- CofO Issued on 4/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2021 | ZAW HAN |
| Corrections Issued | 8/17/2021 | ZAW HAN |
| Quality Review Completed | 8/24/2021 | WING SUEN |
| Applicant returned to address corrections | 10/21/2021 | ZAW HAN |
| Plan Check Approved | 10/28/2021 | ZAW HAN |
| Issued | 11/15/2021 | APPLICANT |
| Building Plans Picked Up | 11/23/2021 | APPLICANT |
| CofO in Progress | 4/6/2022 | GRANT WOODS |
| Permit Finaled | 4/7/2022 | HENRY BAGHDASSARIAN |
| Permit Finaled | 4/7/2022 | HENRY BAGHDASSARIAN |
| CofO Issued | 4/7/2022 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Specific Plan | Cleared | 9/7/2021 | TAIMOUR TANAVOLI |
| Miscellaneous | Cleared | 9/8/2021 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2021 | DENNIS BRAGIN |
| Specific Plan | Cleared | 9/13/2021 | ESTHER AMAYA |
| ZA Case | Cleared | 9/17/2021 | DANIEL CORONADO |
| Grading Pre-Inspection | Cleared | 10/8/2021 | PATRICK MISCHLICH |
| Excavation more than 5-ft deep | Cleared | 10/28/2021 | CALOSHA APPROVED |
Contact Information
| Contractor | Electro Construction Corp; Lic. No.: 95881-B | 2225 WINDSOR AVENUE ALTADENA, CA 91001 |
Inspector Information
| DANIEL ARMENTA, (310) 914-3925 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/6/2021 | Approved | GRANT WOODS |
| Deputy Grading | 12/7/2021 | Approved | GRANT WOODS |
| Piling/Pier/Caisson | 12/7/2021 | Not Ready for Inspection | GRANT WOODS |
| Piling/Pier/Caisson | 12/8/2021 | Conditional Approval | GRANT WOODS |
| Final | 3/9/2022 | Conditional Approval | GRANT WOODS |