5430 N BEN AVE 91607

Certificate Information: 5430 N BEN AVE 91607

Application / Permit
21020-10000-01234
Plan Check / Job No.
B21LA10815
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
CONSTRUCTION OF SWIMMING POOL & SPA PER STANDARD PLAN
Permit Issued
Issued on 9/7/2021
Issuing Office
Current Status
CofO Issued on 7/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/9/2021 APPLICANT
Assigned to Plan Check Engineer 6/10/2021 RICARDO RAMIREZ
Corrections Issued 6/10/2021 RICARDO RAMIREZ
Applicant returned to address corrections 7/5/2021 SINA KHOSRAVI
Applicant returned to address corrections 7/25/2021 AUNG SOE
Plan Check Approved 8/24/2021 TSE MING HUANG
Issued 9/7/2021 APPLICANT
Building Plans Picked Up 9/8/2021 APPLICANT
CofO in Progress 7/15/2022 THOMAS FINNILA
CofO in Progress 7/15/2022 THOMAS FINNILA
Permit Finaled 7/23/2022 MICHAEL SMITH
CofO Issued 7/23/2022 MICHAEL SMITH
Permit Finaled 7/23/2022 MICHAEL SMITH

Permit Application Clearance Information

Specific Plan Cleared 6/25/2021 ANDREW JORGENSEN
ZI Cleared 6/25/2021 ANDREW JORGENSEN
ZI Cleared 6/25/2021 ANDREW JORGENSEN

Contact Information

Contractor S B W Pools Inc; Lic. No.: 960525-C53 8267 MARMAY PL      SUN VALLEY, CA 91352
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/17/2021 Approved JENNIFER RABUCHIN
Grounding or Bonding 9/17/2021 Approved JENNIFER RABUCHIN
Rough-Plumbing 9/17/2021 Approved JENNIFER RABUCHIN
Deputy Shotcrete 9/24/2021 Conditional Approval THOMAS FINNILA
Grounding or Bonding 10/1/2021 Conditional Approval THOMAS FINNILA
Enclosure/Fence 1/19/2022 Corrections Issued JENNIFER RABUCHIN
Enclosure/Fence 1/27/2022 Corrections Issued MISAEL ESPARZA
Enclosure/Fence 2/4/2022 Corrections Issued THOMAS FINNILA
Final 2/25/2022 Corrections Issued THOMAS FINNILA
Pre-Gunite 2/25/2022 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 2/25/2022 SGSOV Approved THOMAS FINNILA
Final 3/30/2022 Corrections Issued DAVID MATSON
Equipment Noise Level 4/12/2022 Approved FELIPE PENICHE
Pool Equipment Noise Test 4/12/2022 Approved FELIPE PENICHE
Final 4/19/2022 Corrections Issued THOMAS FINNILA
Final 6/15/2022 Corrections Issued THOMAS FINNILA
Final 6/27/2022 OK to Issue CofO THOMAS FINNILA