9776 W PEAVINE DR 90210

Certificate Information: 9776 W PEAVINE DR 90210

Application / Permit
21020-10000-01127
Plan Check / Job No.
B21LA10000
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
(N) TWO RETAINING WALL
Permit Issued
Issued on 5/12/2023
Issuing Office
Valley
Current Status
Issued on 5/12/2023

Permit Application Status History

Submitted 5/25/2021 APPLICANT
Assigned to Plan Check Engineer 6/17/2021 DANIEL YIP
Corrections Issued 6/28/2021 DANIEL YIP
Quality Review Completed 7/12/2021 JASON HEALEY
Building Plans Picked Up 7/16/2021 APPLICANT
Applicant returned to address corrections 6/22/2022 DANIEL YIP
Applicant returned to address corrections 3/15/2023 DANIEL YIP
Plan Check Approved 3/29/2023 DANIEL YIP
Issued 5/12/2023 APPLICANT

Permit Application Clearance Information

Landscape for retaining wall Cleared 1/31/2022 ANACANY HURTADO
Low Impact Development Cleared 3/3/2022 ORVAL HERNANDEZ-MARCI
Excavation more than 5-ft deep Cleared 6/22/2022 CALOSHA APPROVED
Grading Pre-Inspection Cleared 6/22/2022 DANIEL YIP

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ROBERT PINA, (213) 482-0404 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/7/2023 Corrections Issued ALEXANDER HELFER
Piling/Pier/Caisson 9/7/2023 Partial Approval ALEXANDER HELFER
Piling/Pier/Caisson 9/26/2023 Approved ALEXANDER HELFER
Excavation/Setback/Form/Re-Bar 5/7/2024 Approved ALEXANDER HELFER
Masonry Wall/Backfill 5/22/2024 Approved ALEXANDER HELFER
Piling/Pier/Caisson 3/5/2025 Partial Approval JONATHAN HOM
Deputy Reinf. Concrete 3/6/2025 Approved JONATHAN HOM
Excavation/Setback/Form/Re-Bar 3/7/2025 Corrections Issued JONATHAN HOM
Piling/Pier/Caisson 3/27/2025 Approved ALEXANDER HELFER
Deputy Reinf. Concrete 4/1/2025 Corrections Issued ALEXANDER HELFER
Excavation/Setback/Form/Re-Bar 4/14/2025 Partial Approval ALEXANDER HELFER
Excavation/Setback/Form/Re-Bar 5/5/2025 Conditional Approval ROBERT PINA
Deputy Reinf. Concrete 5/22/2025 Conditional Approval ROBERT PINA
Excavation/Setback/Form/Re-Bar 6/17/2025 Partial Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 7/3/2025 Conditional Approval ALEXANDER HELFER
Deputy Reinf. Concrete 7/10/2025 Conditional Approval RUSSELL BONVOULOIR
Masonry Wall/Backfill 8/20/2025 Approved ROBERT PINA