901 N STONE CANYON ROAD 90077
Certificate Information: 901 N STONE CANYON ROAD 90077
- Application / Permit
- 21020-10000-01109
- Plan Check / Job No.
- B21LA09757
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- (N) DRIVEWAY BRIDGE STRUCTURE (N) DRIVEWAY GATE STRUCTURE.
- Permit Issued
- Issued on 10/28/2021
- Issuing Office
- Current Status
- Permit Finaled on 5/31/2023
Permit Application Status History
| Submitted | 5/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | JOE VO |
| Corrections Issued | 6/1/2021 | JOE VO |
| Quality Review Completed | 6/1/2021 | KEN GILL |
| Plan Check Approved | 10/19/2021 | JOE VO |
| Issued | 10/28/2021 | APPLICANT |
| Building Plans Picked Up | 10/29/2021 | APPLICANT |
| Permit Finaled | 5/30/2023 | CHRISTOPHER WILSON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Hanover Builders Inc; Lic. No.: 709353-B | 141 DUESENBERG DRIVE STE 6 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Baad,, Katherine Firestone; Lic. No.: C64669 | 5232 ZAKON RD TORRANCE, CA 90505 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 11/4/2021 | Partial Approval | CHRISTOPHER WILSON |
| Pre-Inspection | 11/4/2021 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 11/19/2021 | Conditional Approval | CHRISTOPHER WILSON |
| Piling/Pier/Caisson | 11/22/2021 | Partial Approval | BRENDAN LOONEY |
| Reinforced Concrete Frame | 11/22/2021 | Partial Approval | BRENDAN LOONEY |
| Deputy Reinf. Concrete | 11/29/2021 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 12/8/2021 | Conditional Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 12/10/2021 | Approved | CHRISTOPHER WILSON |
| Reinforced Concrete Frame | 12/10/2021 | Approved | CHRISTOPHER WILSON |
| Special/Order Compliance | 12/16/2021 | Partial Approval | RYAN SALAZAR |
| Final | 2/21/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Final | 5/16/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Final | 5/22/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Final | 5/30/2023 | Permit Finaled | CHRISTOPHER WILSON |