1221 N FIGUEROA PL 90744

Certificate Information: 1221 N FIGUEROA PL 90744

Application / Permit
21020-10000-00236
Plan Check / Job No.
B21LA02153
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(61) Use of Land
Work Description
USE OF LAND FOR 75 EMERGENCY SLEEPING CABINS (75 BEDS TOTAL), 1 STORAGE UNIT, 1 GUARDHOUSE AND 1 HYGIENE TRAILER PER CBC APPENDIX O AND GOVERNMENT CODE SECTION 8698, et seq. A BRIDGE HOME.
Permit Issued
Issued on 3/25/2021
Issuing Office
Current Status
CofO Issued on 6/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/9/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 KEVIN MORALES
Corrections Issued 2/23/2021 KEVIN MORALES
Quality Review Completed 2/23/2021 EUGENE BARBEAU
Building Plans Picked Up 2/23/2021 APPLICANT
Plan Check Approved 3/24/2021 KEVIN MORALES
Issued 3/25/2021 APPLICANT
TCO Issued (Expire Date: 11-23-2021) 5/27/2021 NICK LAROCCA
CofO in Progress 6/23/2021 JOEY BUCHANAN
Permit Finaled 6/23/2021 NICK LAROCCA
CofO Issued 6/23/2021 NICK LAROCCA
Permit Finaled 6/23/2021 NICK LAROCCA
Disabled Access Plans Picked Up 2/23/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/3/2021 CHINH DINH
Permit Cleared 3/3/2021 CHINH DINH
Roof/Waste drainage to street Cleared 3/3/2021 CHINH DINH
City owned building/parcel Cleared 3/4/2021 DANIEL TARICA
Eng Process Fee Ord 176,300 Cleared 3/15/2021 CHINH DINH
Hydrant and Access approval Cleared 3/16/2021 MATTHEW CRAIG
DAS Clearance Cleared 3/20/2021 EUGENE BARBEAU
Sewer availability Cleared 3/24/2021 CHINH DINH

Contact Information

Contractor Access Pacific Inc; Lic. No.: 930437-B 2835 SIERRA GRANDE ST      PASADENA, CA 91107
Engineer Sarujikamjornwattana,, Phaitoon; Lic. No.: S4850 7069 E HANBURY ST      LONG BEACH, CA 90808

Inspector Information

MICHAEL PETRUSKO, (310) 732-4552 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/26/2021 Approved JOEY BUCHANAN
Special/Order Compliance 4/6/2021 Approved JOEY BUCHANAN
Pre-Inspection 5/6/2021 Approved JOEY BUCHANAN
Pre-Inspection 5/10/2021 Approved NICK LAROCCA
Final 5/14/2021 Corrections Issued JOEY BUCHANAN
Final 5/24/2021 Not Ready for Inspection JOEY BUCHANAN
Final 5/26/2021 OK for TCO JOEY BUCHANAN
Final 6/16/2021 Not Ready for Inspection NICK LAROCCA
Final 6/21/2021 OK to Issue CofO JOEY BUCHANAN