9502 S COMPTON AVE 90002

Certificate Information: 9502 S COMPTON AVE 90002

Application / Permit
21020-10000-00233
Plan Check / Job No.
B21LA02148
Group
Building
Type
Nonbldg-New
Sub-Type
Apartment
Primary Use
(23) Fence Wall
Work Description
ePlan deferred item. New concrete block walls to create trash enclosure for new apartment building.
Permit Issued
Issued on 4/16/2021
Issuing Office
Current Status
Permit Finaled on 11/4/2022

Permit Application Status History

Submitted 2/8/2021 APPLICANT
Assigned to Plan Check Engineer 2/10/2021 VU NGUYEN
Corrections Issued 2/17/2021 VU NGUYEN
Quality Review Completed 2/19/2021 EUGENE BARBEAU
Plan Check Approved 3/12/2021 VU NGUYEN
Issued 4/16/2021 APPLICANT
Permit Finaled 10/28/2022 RUSSELL BONVOULOIR

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Gundry Partners Lp; Lic. No.: 1006248-B 17434 BELLFLOWER BLVD   SUITE 300    BELLFLOWER, CA 90706
Engineer Tavares,, Ralph Monteiro; Lic. No.: C60484 11590 WEST BERNARDO COURT STE 100      SAN DIEGO, CA 92128

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Masonry Wall/Backfill 3/10/2022 Conditional Approval DARRYL ARNOLD
Excavation/Setback/Form/Re-Bar 3/15/2022 Partial Approval RUSSELL BONVOULOIR
Masonry Wall/Backfill 3/15/2022 Partial Approval RUSSELL BONVOULOIR
Final 10/28/2022 Permit Finaled RUSSELL BONVOULOIR