232 N BENTLEY CIR 90049
Certificate Information: 232 N BENTLEY CIR 90049
- Application / Permit
- 21020-10000-00152
- Plan Check / Job No.
- B21LA01442
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- NEW 10 FT TALL RETAINING WALL (206 LF)
- Permit Issued
- Issued on 1/24/2022
- Issuing Office
- Valley
- Current Status
- Issued on 1/24/2022
Permit Application Status History
| Submitted | 1/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2021 | STARR CHEN |
| Corrections Issued | 2/6/2021 | STARR CHEN |
| Quality Review Completed | 2/9/2021 | ALLEN MANALANSAN |
| Building Plans Picked Up | 2/16/2021 | APPLICANT |
| Applicant returned to address corrections | 4/9/2021 | STARR CHEN |
| Applicant returned to address corrections | 10/28/2021 | STARR CHEN |
| Applicant returned to address corrections | 11/5/2021 | STARR CHEN |
| Applicant returned to address corrections | 12/3/2021 | STARR CHEN |
| Applicant returned to address corrections | 12/10/2021 | STARR CHEN |
| Plan Check Approved | 1/13/2022 | STARR CHEN |
| Issued | 1/24/2022 | APPLICANT |
Permit Application Clearance Information
| Landscape for retaining wall | Cleared | 2/25/2021 | JOE LUCKEY |
| GPI Written Notices | Cleared | 12/10/2021 | STARR CHEN |
| Grading Pre-Inspection | Cleared | 12/10/2021 | STARR CHEN |
Contact Information
| Architect | Hwangbo,, James Sungkyum; Lic. No.: C37990 | 421 S LA FAYETTE PARK PLACE #604 LOS ANGELES, CA 90057 |
| Contractor | I R V Design And Construction Inc; Lic. No.: 909508-B | 11358 SHELDON STREET SUN VALLEY, CA 91352 |
| Engineer | Moeini,, Soheil; Lic. No.: C84000 | 11022 SANTA MONICA BLVD STE 440 LOS ANGELES, CA 90025 |
| Engineer | Samadzadeh,, Hooman Ali; Lic. No.: C87661 | 22430 CRISWELL ST WEST HILLS, CA 91307 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/4/2022 | Corrections Issued | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 2/10/2022 | Partial Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 2/28/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 2/28/2022 | Corrections Issued | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 3/4/2022 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 3/4/2022 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 3/29/2022 | Conditional Approval | CARLOS MATAMOROS |
| Reinforced Concrete Frame | 3/30/2022 | Partial Approval | CARLOS MATAMOROS |
| Reinforced Masonry Frame | 3/30/2022 | Partial Approval | CARLOS MATAMOROS |
| Deputy Shotcrete | 4/5/2022 | Conditional Approval | CARLOS MATAMOROS |
| Masonry Wall/Backfill | 4/26/2022 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 5/11/2022 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 5/17/2022 | Corrections Issued | CARLOS MATAMOROS |
| Reinforced Concrete Frame | 5/17/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Reinforced Masonry Frame | 5/17/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 5/19/2022 | Partial Approval | CARLOS MATAMOROS |
| Reinforced Concrete Frame | 5/19/2022 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 5/20/2022 | Conditional Approval | CARLOS MATAMOROS |
| Reinforced Concrete Frame | 5/24/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Reinforced Concrete Frame | 5/26/2022 | Approved | CARLOS MATAMOROS |
| Final | 8/20/2024 | Corrections Issued | CARLOS MATAMOROS |
| Final | 8/27/2024 | Not Ready for Inspection | CARLOS MATAMOROS |