232 N BENTLEY CIR 90049

Certificate Information: 232 N BENTLEY CIR 90049

Application / Permit
21020-10000-00152
Plan Check / Job No.
B21LA01442
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
NEW 10 FT TALL RETAINING WALL (206 LF)
Permit Issued
Issued on 1/24/2022
Issuing Office
Valley
Current Status
Issued on 1/24/2022

Permit Application Status History

Submitted 1/27/2021 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 STARR CHEN
Corrections Issued 2/6/2021 STARR CHEN
Quality Review Completed 2/9/2021 ALLEN MANALANSAN
Building Plans Picked Up 2/16/2021 APPLICANT
Applicant returned to address corrections 4/9/2021 STARR CHEN
Applicant returned to address corrections 10/28/2021 STARR CHEN
Applicant returned to address corrections 11/5/2021 STARR CHEN
Applicant returned to address corrections 12/3/2021 STARR CHEN
Applicant returned to address corrections 12/10/2021 STARR CHEN
Plan Check Approved 1/13/2022 STARR CHEN
Issued 1/24/2022 APPLICANT

Permit Application Clearance Information

Landscape for retaining wall Cleared 2/25/2021 JOE LUCKEY
GPI Written Notices Cleared 12/10/2021 STARR CHEN
Grading Pre-Inspection Cleared 12/10/2021 STARR CHEN

Contact Information

Architect Hwangbo,, James Sungkyum; Lic. No.: C37990 421 S LA FAYETTE PARK PLACE #604      LOS ANGELES, CA 90057
Contractor I R V Design And Construction Inc; Lic. No.: 909508-B 11358 SHELDON STREET      SUN VALLEY, CA 91352
Engineer Moeini,, Soheil; Lic. No.: C84000 11022 SANTA MONICA BLVD STE 440      LOS ANGELES, CA 90025
Engineer Samadzadeh,, Hooman Ali; Lic. No.: C87661 22430 CRISWELL ST      WEST HILLS, CA 91307

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/4/2022 Corrections Issued CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 2/10/2022 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 2/28/2022 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 2/28/2022 Corrections Issued CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 3/4/2022 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 3/4/2022 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 3/29/2022 Conditional Approval CARLOS MATAMOROS
Reinforced Concrete Frame 3/30/2022 Partial Approval CARLOS MATAMOROS
Reinforced Masonry Frame 3/30/2022 Partial Approval CARLOS MATAMOROS
Deputy Shotcrete 4/5/2022 Conditional Approval CARLOS MATAMOROS
Masonry Wall/Backfill 4/26/2022 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 5/11/2022 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 5/17/2022 Corrections Issued CARLOS MATAMOROS
Reinforced Concrete Frame 5/17/2022 Not Ready for Inspection CARLOS MATAMOROS
Reinforced Masonry Frame 5/17/2022 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 5/19/2022 Partial Approval CARLOS MATAMOROS
Reinforced Concrete Frame 5/19/2022 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 5/20/2022 Conditional Approval CARLOS MATAMOROS
Reinforced Concrete Frame 5/24/2022 Corrections Issued CHRISTOPHER WILSON
Reinforced Concrete Frame 5/26/2022 Approved CARLOS MATAMOROS
Final 8/20/2024 Corrections Issued CARLOS MATAMOROS
Final 8/27/2024 Not Ready for Inspection CARLOS MATAMOROS