427 S HEWITT ST 90013

Certificate Information: 427 S HEWITT ST 90013

Application / Permit
21016-30001-15817
Plan Check / Job No.
B23WL00337
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
SUPPLEMENTAL TO PERMIT NO. 21016-30000-15817 TO INCREASE RESTAURANT AREA FROM 3,056 SQ. FT. TO 4,548 SQ. FT. REDUCING THE ADJACENT OFFICE TENANT SPACE. LEAVE ADJACENT OFFICE TENANT SPACE AS CORE AND SHELL ONLY. REVISE RESTAURANT FLOOR PLANS AND RESTROOMS DUE TO INCREASE IN AREA.
Permit Issued
Issued on 5/8/2023
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 6/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/8/2023 APPLICANT
Assigned to Plan Check Engineer 2/23/2023 SERGIO SILVA
Green Plans Picked Up 2/24/2023 APPLICANT
Disabled Access Plans Picked Up 3/9/2023 APPLICANT
Corrections Issued 3/10/2023 SERGIO SILVA
Quality Review Completed 3/14/2023 KAVIAN REFAHI
Building Plans Picked Up 3/17/2023 APPLICANT
Plan Check Approved 4/19/2023 SERGIO SILVA
Issued 5/8/2023 APPLICANT
Permit Finaled 6/3/2024 RONALD JIMENEZ

Permit Application Clearance Information

Food Service Establishment Cleared 4/13/2023 RAMESHBHAIR PATEL
Green Code Cleared 4/14/2023 SERGIO SILVA
Fire Marshal Fire Life Safety Cleared 4/17/2023 MENOA AGHAJANI
Eng Process Fee Ord 176,300 Cleared 4/18/2023 TREVOR QUAN
Sewer availability Cleared 4/18/2023 TREVOR QUAN
DAS Clearance Cleared 4/19/2023 SERGIO SILVA
Food establishment approval Cleared 4/19/2023 LACDHS APPROVED

Contact Information

Architect Brunn,, Dan; Lic. No.: C31368 737 S LONGWOOD AVENUE      LOS ANGELES, CA 90005
Contractor Gundry Partners Lp; Lic. No.: 1006248-B 17434 BELLFLOWER BLVD   SUITE 300    BELLFLOWER, CA 90706
Engineer Labib,, Youhanna T.; Lic. No.: S4549 319 MAIN STREET      EL SEGUNDO, CA 90245

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Drywall Nailing 9/25/2023 Not Ready for Inspection JULIAN CAPUCETTI
Green Building Rough 9/25/2023 Partial Approval JULIAN CAPUCETTI
Light Gage Steel Frame 9/25/2023 Partial Approval JULIAN CAPUCETTI
METHANE-Rough 9/25/2023 Partial Inspection JULIAN CAPUCETTI
Structural Steel Frame 9/25/2023 Partial Approval JULIAN CAPUCETTI
Drywall Nailing 10/13/2023 Partial Approval KATY RAMIREZ
Green Building Rough 10/13/2023 Approved KATY RAMIREZ
Drywall Nailing 10/24/2023 Partial Approval RICARDO ROBLES
Pre-Inspection 10/31/2023 Partial Inspection KATY RAMIREZ
Drywall Nailing 5/22/2024 Approved RONALD JIMENEZ
Final 5/22/2024 Conditional Approval RONALD JIMENEZ
Green Building Final 5/22/2024 Approved RONALD JIMENEZ
METHANE-Final 5/22/2024 Approved RONALD JIMENEZ
METHANE-Rough 5/22/2024 Approved RONALD JIMENEZ
Reinforced Concrete Frame 5/22/2024 Approved RONALD JIMENEZ
Reinforced Masonry Frame 5/22/2024 Approved RONALD JIMENEZ
Structural Steel Frame 5/22/2024 Approved RONALD JIMENEZ
Final 6/3/2024 Permit Finaled RONALD JIMENEZ