528 E WESTMINSTER AVE 90291
Certificate Information: 528 E WESTMINSTER AVE 90291
- Application / Permit
- 21016-30001-13650
- Plan Check / Job No.
- B22WL02741
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- Supplenental ref to pcis # 21016-30000-13650, for addition to the existing 2-story Duplex
- Permit Issued
- Issued on 12/19/2022
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 6/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2022 | FELIPE HERNANDEZ |
| Corrections Issued | 8/12/2022 | FELIPE HERNANDEZ |
| Quality Review Completed | 8/22/2022 | KAVIAN REFAHI |
| Building Plans Picked Up | 8/23/2022 | APPLICANT |
| Plan Check Approved | 12/13/2022 | KAVIAN REFAHI |
| Issued | 12/19/2022 | APPLICANT |
| Permit Finaled | 6/17/2025 | BOBBY KEY |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 8/12/2022 | RICARDO BOHORQUEZ |
| Sewer availability | Cleared | 8/16/2022 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2022 | JENSON LEE |
| ZA Case | Cleared | 8/25/2022 | SHASHA YU |
| ZA Case | Cleared | 8/25/2022 | SHASHA YU |
| Low Impact Development | Cleared | 11/3/2022 | DEBORA LEITE |
| Coastal Zone | Cleared | 11/18/2022 | KENTON TRINH |
| Miscellaneous | Cleared | 11/18/2022 | KENTON TRINH |
| Roof/Waste drainage to street | Cleared | 11/21/2022 | JENSON LEE |
| Specific Plan | Cleared | 11/30/2022 | IRA BROWN |
Contact Information
| Architect | Osuch,, Edward M; Lic. No.: C32544 | 6191 ST ALBANS STREET # A LOS ANGELES, CA 90042 |
| Contractor | Kara Construction Group Inc; Lic. No.: 1064239-B | 347 W GARFIELD AVE GLENDALE, CA 91204 |
| Engineer | Kang,, Danniel; Lic. No.: S6242 | 18411 CRENSHAW BLVD SUITE 408 TORRANCE, CA 90504 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/4/2023 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 5/4/2023 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 6/10/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Drywall Nailing | 6/10/2025 | Approved | JESUS RODRIGUEZ |
| Final | 6/10/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 6/10/2025 | Approved | JESUS RODRIGUEZ |
| Green Building Final | 6/10/2025 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 6/10/2025 | Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 6/10/2025 | Approved | JESUS RODRIGUEZ |