208 E 76TH PL 90003
Certificate Information: 208 E 76TH PL 90003
- Application / Permit
- 21016-30000-59457
- Plan Check / Job No.
- B21WL05811
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) detached garage and laundry room to an ADU per LAMC 12.22A33(c) and (d) at the rear of the lot. COMPLY WITH DEPARTMENT ORDER effective date 03/31/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 5/23/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2022 | JAHANSHAH POURHASSAN |
| Corrections Issued | 1/11/2022 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 4/4/2022 | EDWIN ESPIN |
| Building Plans Picked Up | 5/3/2022 | APPLICANT |
| Plan Check Approved | 5/23/2022 | EDWIN ESPIN |
| Issued | 5/23/2022 | APPLICANT |
| CofO in Progress | 3/6/2023 | MEL KHACHATOURIAN |
| Permit Finaled | 3/10/2023 | BRUCE TODD |
| CofO Issued | 3/10/2023 | BRUCE TODD |
| Permit Finaled | 3/10/2023 | BRUCE TODD |
Permit Application Clearance Information
| Address approval | Cleared | 1/14/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 1/14/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2022 | AMAAN MALIK |
| Construction near power lines | Cleared | 3/4/2022 | TINA MIRANDA |
Contact Information
| Contractor | Nelson General Building Contractor; Lic. No.: 649194-B | 4227 S WESTERN AVE LOS ANGELES, CA 90062 |
Inspector Information
| JEREMY TODD, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARVIN FONSECA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GUEVARA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/3/2022 | Partial Approval | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 6/21/2022 | Corrections Issued | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 6/21/2022 | Corrections Issued | MEL KHACHATOURIAN |
| HVAC-Rough | 6/21/2022 | Corrections Issued | MEL KHACHATOURIAN |
| PLUMBING-Rough | 6/21/2022 | Corrections Issued | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 6/24/2022 | Corrections Issued | MEL KHACHATOURIAN |
| HVAC-Rough | 6/24/2022 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 6/24/2022 | Corrections Issued | MEL KHACHATOURIAN |
| Underground Mechanical | 6/24/2022 | Partial Approval | MEL KHACHATOURIAN |
| Special/Order Compliance | 6/27/2022 | Not Ready for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 6/30/2022 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 6/30/2022 | Approved | MEL KHACHATOURIAN |
| HVAC-Rough | 6/30/2022 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 6/30/2022 | Approved | MEL KHACHATOURIAN |
| Insulation | 7/1/2022 | Approved | MEL KHACHATOURIAN |
| Drywall Nailing | 7/6/2022 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 7/6/2022 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 10/3/2022 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 11/30/2022 | Approved | MEL KHACHATOURIAN |
| Final | 11/30/2022 | Conditional Approval | MEL KHACHATOURIAN |
| HVAC-Final | 11/30/2022 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Final | 11/30/2022 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 11/30/2022 | SGSOV Approved | MEL KHACHATOURIAN |
| Smoke Detectors | 11/30/2022 | Approved | MEL KHACHATOURIAN |
| Wood Frame | 11/30/2022 | Approved | MEL KHACHATOURIAN |