821 E TRACTION AVE 90013
Certificate Information: 821 E TRACTION AVE 90013
- Application / Permit
- 21016-30000-59445
- Plan Check / Job No.
- B21WL05806
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- Office tenant improvement. *** see comments ***
- Permit Issued
- Issued on 6/2/2022
- Issuing Office
- Current Status
- Permit Finaled on 12/13/2022
Permit Application Status History
| Submitted | 1/17/2022 | APPLICANT |
| Green Plans Picked Up | 2/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/3/2022 | KAVIAN REFAHI |
| Corrections Issued | 2/9/2022 | KAVIAN REFAHI |
| Quality Review Completed | 2/15/2022 | FELIX FIGUEROA |
| Applicant returned to address corrections | 3/16/2022 | KAVIAN REFAHI |
| Applicant returned to address corrections | 3/18/2022 | KAVIAN REFAHI |
| Building Plans Picked Up | 3/21/2022 | APPLICANT |
| Applicant returned to address corrections | 4/13/2022 | KAVIAN REFAHI |
| Plan Check Approved | 5/23/2022 | KAVIAN REFAHI |
| No Progress | 5/23/2022 | KAVIAN REFAHI |
| Plan Check Approved | 5/26/2022 | KAVIAN REFAHI |
| Issued | 6/2/2022 | APPLICANT |
| Permit Finaled | 12/13/2022 | MARK FERRARI |
Permit Application Clearance Information
| Green Code | Cleared | 4/22/2022 | RICHARD GARCIA |
| DAS Clearance | Cleared | 5/19/2022 | KAVIAN REFAHI |
Contact Information
| Contractor | Swinerton Builders; Lic. No.: 92-B | 2001 CLAYTON RD 7TH FLOOR LEGAL CONCORD, CA 94520 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 6/7/2022 | Partial Inspection | MARK FERRARI |
| Drywall Nailing | 6/13/2022 | Partial Approval | MARK FERRARI |
| Light Gage Steel Frame | 6/24/2022 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 6/28/2022 | Approved | MARK FERRARI |
| Drywall Nailing | 7/1/2022 | Partial Approval | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 7/7/2022 | Corrections Issued | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 7/8/2022 | Partial Approval | MARK FERRARI |
| Wood Frame | 7/21/2022 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 7/22/2022 | Partial Approval | MARK FERRARI |
| Drywall Nailing | 7/25/2022 | Partial Approval | MARK FERRARI |
| Special/Order Compliance | 8/10/2022 | Partial Approval | MARK FERRARI |
| Final | 9/22/2022 | Partial Inspection | MARK FERRARI |
| Green Building Final | 9/22/2022 | Not Ready for Inspection | MARK FERRARI |
| Green Building Rough | 9/22/2022 | Approved | MARK FERRARI |
| METHANE-Final | 9/22/2022 | Approved | MARK FERRARI |
| METHANE-Rough | 9/22/2022 | Approved | MARK FERRARI |
| Reinforced Masonry Frame | 9/22/2022 | Approved | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 9/22/2022 | SGSOV Not Ready | MARK FERRARI |
| Smoke Detectors | 9/22/2022 | Not Ready for Inspection | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 9/27/2022 | SGSOV Not Ready | MARK FERRARI |
| Final | 9/28/2022 | Conditional Approval | MARK FERRARI |
| Green Building Final | 9/28/2022 | Approved | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 9/28/2022 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 9/28/2022 | Approved | MARK FERRARI |
| Final | 12/13/2022 | Permit Finaled | MARK FERRARI |