3418 1/4-1/2 W 77TH ST 90043

Certificate Information: 3418 1/4-1/2 W 77TH ST 90043

Application / Permit
21016-30000-59399
Plan Check / Job No.
B21WL05787
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Attached Garage conversion to ADU.PER LAMC 12.22 A.33(c) AND (e). Per engineering design.
Permit Issued
Issued on 4/5/2022
Issuing Office
Current Status
CofO Issued on 12/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/2/2022 APPLICANT
Assigned to Plan Check Engineer 1/6/2022 ALFREDO JARA
Corrections Issued 1/10/2022 ALFREDO JARA
Plan Check Approved 3/10/2022 ALFREDO JARA
Building Plans Picked Up 3/14/2022 APPLICANT
Issued 4/5/2022 APPLICANT
CofO in Progress 8/11/2022 ENRIQUE MIRELES
Permit Finaled 12/13/2022 DEROLD HAUFF
CofO Issued 12/13/2022 DEROLD HAUFF
Permit Finaled 12/13/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/12/2022 CINDY QI
Roof/Waste drainage to street Cleared 1/12/2022 CINDY QI
Sewer availability Cleared 1/12/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 1/18/2022 CINDY QI
Tenant Habitability Plan Cleared 2/16/2022 RICHARD BRINSON

Contact Information

Contractor Yakov Design & Build; Lic. No.: 1067993-B 5535 WESTLAWN AVE APT 376      .LOS ANGELES, CA 90066
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22121 CLARENDON ST APT 340      WOODLAND HILLS, CA 91367

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/7/2022 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 4/8/2022 Approved ENRIQUE MIRELES
Underground Mechanical 4/18/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 4/28/2022 Approved ENRIQUE MIRELES
HVAC-Rough 4/28/2022 Approved ENRIQUE MIRELES
Insulation 4/28/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 4/28/2022 Approved ENRIQUE MIRELES
Sewer 4/28/2022 Approved ENRIQUE MIRELES
Wood Frame 4/28/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 6/1/2022 Approved ENRIQUE MIRELES
Drywall Nailing 6/6/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 6/8/2022 Corrections Issued ENRIQUE MIRELES
Interior/Exterior Lathing 6/10/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Final 7/28/2022 Not Ready for Inspection SABAS ALONSO
Final 7/28/2022 Not Ready for Inspection SABAS ALONSO
HVAC-Final 7/28/2022 Not Ready for Inspection SABAS ALONSO
PLUMBING-Final 7/28/2022 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 7/28/2022 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 7/28/2022 Approved SABAS ALONSO
Final 8/4/2022 Corrections Issued ENRIQUE MIRELES
Final 8/10/2022 OK to Issue CofO ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 8/10/2022 SGSOV Approved ENRIQUE MIRELES