3418 1/4-1/2 W 77TH ST 90043
Certificate Information: 3418 1/4-1/2 W 77TH ST 90043
- Application / Permit
- 21016-30000-59399
- Plan Check / Job No.
- B21WL05787
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Attached Garage conversion to ADU.PER LAMC 12.22 A.33(c) AND (e). Per engineering design.
- Permit Issued
- Issued on 4/5/2022
- Issuing Office
- Current Status
- CofO Issued on 12/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2022 | ALFREDO JARA |
| Corrections Issued | 1/10/2022 | ALFREDO JARA |
| Plan Check Approved | 3/10/2022 | ALFREDO JARA |
| Building Plans Picked Up | 3/14/2022 | APPLICANT |
| Issued | 4/5/2022 | APPLICANT |
| CofO in Progress | 8/11/2022 | ENRIQUE MIRELES |
| Permit Finaled | 12/13/2022 | DEROLD HAUFF |
| CofO Issued | 12/13/2022 | DEROLD HAUFF |
| Permit Finaled | 12/13/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/12/2022 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 1/12/2022 | CINDY QI |
| Sewer availability | Cleared | 1/12/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 1/18/2022 | CINDY QI |
| Tenant Habitability Plan | Cleared | 2/16/2022 | RICHARD BRINSON |
Contact Information
| Contractor | Yakov Design & Build; Lic. No.: 1067993-B | 5535 WESTLAWN AVE APT 376 .LOS ANGELES, CA 90066 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22121 CLARENDON ST APT 340 WOODLAND HILLS, CA 91367 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/7/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 4/8/2022 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 4/18/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 4/28/2022 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 4/28/2022 | Approved | ENRIQUE MIRELES |
| Insulation | 4/28/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 4/28/2022 | Approved | ENRIQUE MIRELES |
| Sewer | 4/28/2022 | Approved | ENRIQUE MIRELES |
| Wood Frame | 4/28/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 6/1/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 6/6/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 6/8/2022 | Corrections Issued | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 6/10/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 7/28/2022 | Not Ready for Inspection | SABAS ALONSO |
| Final | 7/28/2022 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Final | 7/28/2022 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Final | 7/28/2022 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 7/28/2022 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 7/28/2022 | Approved | SABAS ALONSO |
| Final | 8/4/2022 | Corrections Issued | ENRIQUE MIRELES |
| Final | 8/10/2022 | OK to Issue CofO | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 8/10/2022 | SGSOV Approved | ENRIQUE MIRELES |