10386 W ILONA AVE 90064
Certificate Information: 10386 W ILONA AVE 90064
- Application / Permit
- 21016-30000-58815
- Plan Check / Job No.
- B21WL05660
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conver (E) Garage to Accesry Dwelling Unit per GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 8/26/2022
- Issuing Office
- Current Status
- CofO Issued on 12/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2021 | EDWIN ESPIN |
| Corrections Issued | 12/23/2021 | EDWIN ESPIN |
| Applicant returned to address corrections | 6/27/2022 | EDWIN ESPIN |
| Applicant returned to address corrections | 8/16/2022 | ALFREDO JARA |
| Plan Check Approved | 8/22/2022 | ALFREDO JARA |
| Issued | 8/26/2022 | APPLICANT |
| Building Plans Picked Up | 8/30/2022 | APPLICANT |
| CofO in Progress | 12/2/2023 | MICHAEL PELHAM |
| Permit Finaled | 12/6/2023 | DANIEL ORRANTE |
| CofO Issued | 12/6/2023 | DANIEL ORRANTE |
| Permit Finaled | 12/6/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/27/2022 | JENSON LEE |
| Sewer availability | Cleared | 4/27/2022 | JENSON LEE |
| Roof/Waste drainage to street | Cleared | 6/13/2022 | JENSON LEE |
| Grading Pre-Inspection | Cleared | 7/25/2022 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2022 | CATHERINE ADROVER |
| Construction within easement | Cleared | 8/4/2022 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Alexander,, Andy; Lic. No.: C84086 | 1615 GRAMERCY AVE TORRANCE, CA 90501 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/23/2022 | Approved | JOHN KIDWELL |
| Sewer | 9/23/2022 | Approved | JOHN KIDWELL |
| Deputy Drilled-In Anchors | 10/5/2022 | Approved | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 10/5/2022 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 10/5/2022 | Partial Approval | STEPHANIE SWANSON |
| Deputy Drilled-In Anchors | 10/12/2022 | Conditional Approval | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 10/12/2022 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 10/12/2022 | Approved | STEPHANIE SWANSON |
| Pre-Inspection | 10/12/2022 | Partial Inspection | STEPHANIE SWANSON |
| Deputy Drilled-In Anchors | 10/20/2022 | Conditional Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 10/27/2022 | Corrections Issued | STEPHANIE SWANSON |
| METHANE-Rough | 10/27/2022 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 11/8/2022 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 11/18/2022 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 11/18/2022 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2022 | Partial Inspection | STEPHANIE SWANSON |
| PLUMBING-Rough | 11/23/2022 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 12/5/2022 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 12/5/2022 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 1/4/2023 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Rough | 1/4/2023 | Partial Approval | STEPHANIE SWANSON |
| Insulation | 4/7/2023 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 4/12/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 4/12/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2023 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 4/12/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 4/28/2023 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 5/1/2023 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 5/5/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 11/20/2023 | Approved | STEPHANIE SWANSON |
| Final | 11/20/2023 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Final | 11/20/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 11/20/2023 | Approved | STEPHANIE SWANSON |
| Final | 12/1/2023 | Conditional Approval | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 12/1/2023 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 12/1/2023 | Approved | STEPHANIE SWANSON |