- Conversion of (E) 2-Car Garage to an ADU per GCS 65852.2(e)(1)(A)** "COMPLY WITH DEPARTMENT ORDER Effective Date 04/15/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 12/5/2022
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2022 | DAVID CASTILLO |
| Corrections Issued | 8/29/2022 | DAVID CASTILLO |
| Building Plans Picked Up | 8/30/2022 | APPLICANT |
| Applicant returned to address corrections | 11/22/2022 | JASON JANGADA |
| Plan Check Approved | 12/2/2022 | ALFREDO JARA |
| Issued | 12/5/2022 | APPLICANT |
| CofO in Progress | 1/31/2024 | MICHAEL LEWIS |
| Permit Finaled | 2/7/2024 | DEROLD HAUFF |
| CofO Issued | 2/7/2024 | DEROLD HAUFF |
| Permit Finaled | 2/7/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/7/2022 | CINDY QI |
| Sewer availability | Cleared | 9/7/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2022 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Southerland,, Richard Charles; Lic. No.: C88965 | 16526 BLACKHAWK ST GRANADA HILLS, CA 91344 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/23/2023 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 2/23/2023 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 3/30/2023 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 4/5/2023 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 9/21/2023 | Corrections Issued | MICHAEL LEWIS |
| Final | 9/21/2023 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 9/21/2023 | Corrections Issued | MICHAEL LEWIS |
| Green Building Rough | 9/21/2023 | Corrections Issued | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 9/21/2023 | SGSOV Not Ready | MICHAEL LEWIS |
| Smoke Detectors | 9/21/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 9/27/2023 | Partial Inspection | MICHAEL LEWIS |
| Green Building Rough | 9/27/2023 | Partial Inspection | MICHAEL LEWIS |
| Pre-Inspection | 10/20/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 11/20/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 11/28/2023 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Rough | 11/28/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 12/7/2023 | Approved | MICHAEL LEWIS |
| Green Building Rough | 12/7/2023 | Approved | MICHAEL LEWIS |
| Insulation | 12/13/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 12/14/2023 | Approved | MICHAEL LEWIS |
| Final | 1/8/2024 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 1/8/2024 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 1/8/2024 | SGSOV Not Ready | MICHAEL LEWIS |
| Final | 1/26/2024 | Partial Inspection | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 1/26/2024 | SGSOV Approved | MICHAEL LEWIS |
| Final | 1/30/2024 | OK to Issue CofO | MICHAEL LEWIS |