10895 W CHALON ROAD 90077
Certificate Information: 10895 W CHALON ROAD 90077
- Application / Permit
- 21016-30000-57426
- Plan Check / Job No.
- B21WL05433
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior and exterior remodel throughout (E) one-story SFD.
- Permit Issued
- Issued on 1/27/2022
- Issuing Office
- Current Status
- Permit Finaled on 5/17/2023
Permit Application Status History
| Submitted | 12/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2021 | JAHANSHAH POURHASSAN |
| Corrections Issued | 12/27/2021 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 1/27/2022 | JAHANSHAH POURHASSAN |
| Issued | 1/27/2022 | APPLICANT |
| Building Plans Picked Up | 1/28/2022 | APPLICANT |
| Permit Finaled | 5/16/2023 | CHRISTOPHER WILSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/27/2022 | JAHANSHAH POURHASSAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Resnick,, Bruce Daniel; Lic. No.: S3293 | 1927 PONTIUS AVE LOS ANGELES, CA 90025 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/11/2022 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 4/11/2022 | Partial Approval | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2022 | Not Ready for Inspection | MICHAEL PELHAM |
| Pre-Inspection | 6/6/2022 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 6/9/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 6/10/2022 | Partial Approval | CHRISTOPHER WILSON |
| Insulation | 6/16/2022 | Partial Approval | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 6/27/2022 | Partial Approval | CHRISTOPHER WILSON |
| Final | 6/29/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Shower Pan | 6/29/2022 | Approved | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2022 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2022 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 7/14/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Rough-Elec/Plmb/HVAC | 7/14/2022 | Partial Approval | CHRISTOPHER WILSON |
| HVAC-Rough | 7/19/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Rough | 7/21/2022 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Rough | 7/25/2022 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 8/19/2022 | Corrections Issued | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 8/26/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 8/26/2022 | Approved | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 9/9/2022 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 9/9/2022 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 9/9/2022 | Approved | CHRISTOPHER WILSON |
| Insulation | 9/19/2022 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 9/19/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 9/27/2022 | Approved | CHRISTOPHER WILSON |
| Drywall Nailing | 10/6/2022 | Approved | CLAYTON GRAHAM |
| Special/Order Compliance | 10/6/2022 | Partial Inspection | STEPHANIE SWANSON |
| Underground Mechanical | 11/16/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Gas Test | 2/1/2023 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 2/1/2023 | SGSOV Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 3/14/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Service/Power Release | 4/18/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Service/Power Release | 4/24/2023 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 4/26/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 5/2/2023 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 5/4/2023 | Approved | CHRISTOPHER WILSON |
| Service/Power Release | 5/4/2023 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Final | 5/9/2023 | Approved | CHRISTOPHER WILSON |
| Final | 5/16/2023 | Permit Finaled | CHRISTOPHER WILSON |
| Green Building Final | 5/16/2023 | Approved | CHRISTOPHER WILSON |
| Smoke Detectors | 5/16/2023 | Approved | CHRISTOPHER WILSON |