6639 1/2 W 6TH ST 90048

Certificate Information: 6639 1/2 W 6TH ST 90048

Application / Permit
21016-30000-57265
Plan Check / Job No.
B21WL05373
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing rear detached 3-car garage into a new ADU per CGS 65852.2(e)(1)(A). ADU is a 1-bedroom/closet, 1 bath and kitchen with living and dining area. front building is an existing 2-story Duplex with two existing dwelling unit (no work proposed for this building)
Permit Issued
Issued on 6/29/2022
Issuing Office
Current Status
CofO Issued on 2/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/8/2021 APPLICANT
Assigned to Plan Check Engineer 12/9/2021 RICHARD GARCIA
Corrections Issued 12/11/2021 RICHARD GARCIA
Applicant returned to address corrections 2/3/2022 EDWIN ESPIN
Building Plans Picked Up 2/7/2022 APPLICANT
Plan Check Approved 3/16/2022 EDWIN ESPIN
Issued 6/29/2022 APPLICANT
CofO in Progress 2/14/2023 CLAYTON GRAHAM
Permit Finaled 2/16/2023 DANIEL ORRANTE
CofO Issued 2/16/2023 DANIEL ORRANTE
Permit Finaled 2/16/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/4/2022 TREVOR QUAN
Roof/Waste drainage to street Cleared 1/4/2022 TREVOR QUAN
Sewer availability Cleared 1/4/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 1/5/2022 TREVOR QUAN
Construction within easement Cleared 3/10/2022 RIDWAN HARDY

Contact Information

Contractor Kwc Construction Inc; Lic. No.: 972615-B 26803 STONEGATE DRIVE      VALENCIA, CA 91381
Engineer Kang,, Danniel; Lic. No.: S6242 18411 CRENSHAW BLVD   SUITE 408    TORRANCE, CA 90504

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/3/2022 Partial Approval EVAN COOPER
PLUMBING-Rough 8/3/2022 Partial Approval EVAN COOPER
Footing/Foundation/Slab 8/17/2022 Approved EVAN COOPER
Deputy Wood Construction 10/12/2022 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 10/12/2022 Partial Approval EVAN COOPER
Green Building Rough 10/12/2022 Not Ready for Inspection EVAN COOPER
METHANE-Rough 10/12/2022 Approved EVAN COOPER
Underground Mechanical 10/12/2022 Partial Approval EVAN COOPER
ELECTRICAL-Rough 10/18/2022 Approved EVAN COOPER
HVAC-Rough 10/18/2022 Approved EVAN COOPER
PLUMBING-Rough 10/18/2022 Approved EVAN COOPER
Wood Frame 10/18/2022 Approved EVAN COOPER
Insulation 10/26/2022 Corrections Issued JESUS RODRIGUEZ
Insulation 10/31/2022 Approved EVAN COOPER
Sewer 11/3/2022 Approved EVAN COOPER
Drywall Nailing 11/9/2022 Approved GERMAN RODRIGUEZ MENDOZA
Shower Pan 11/10/2022 Approved CLAYTON GRAHAM
Interior/Exterior Lathing 11/18/2022 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 1/13/2023 Approved JEREMY TODD
Final 1/13/2023 Corrections Issued JEREMY TODD
Green Building Final 1/13/2023 Approved JEREMY TODD
Green Building Rough 1/13/2023 Approved JEREMY TODD
SGSOV-Seismic Gas S/O Valve 1/13/2023 SGSOV Approved JEREMY TODD
Smoke Detectors 1/13/2023 Approved JEREMY TODD
ELECTRICAL-Final 1/27/2023 Approved JEREMY TODD
Final 1/27/2023 Conditional Approval JEREMY TODD
HVAC-Final 1/27/2023 Approved JEREMY TODD
PLUMBING-Final 1/27/2023 Approved JEREMY TODD
Final 2/13/2023 OK to Issue CofO CLAYTON GRAHAM