1424 S ABBOT KINNEY BLVD 90291
Certificate Information: 1424 S ABBOT KINNEY BLVD 90291
- Application / Permit
- 21016-30000-56663
- Plan Check / Job No.
- B21WL05358
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- TENANT IMPROVEMENT ALTERATION/REPAIR TO EXISTING 1-STORY TYPE VB COMMERCIAL RETAIL BUILDING. NO CHANGE IN USE, OCCUPANCY, OR PARKING.
- Permit Issued
- Issued on 3/14/2022
- Issuing Office
- Current Status
- Permit Finaled on 10/12/2022
Permit Application Status History
| Submitted | 12/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2021 | SERGIO SILVA |
| Corrections Issued | 12/15/2021 | SERGIO SILVA |
| Quality Review Completed | 12/21/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 3/2/2022 | SERGIO SILVA |
| Plan Check Approved | 3/9/2022 | SERGIO SILVA |
| Issued | 3/14/2022 | APPLICANT |
| Building Plans Picked Up | 3/15/2022 | APPLICANT |
| Permit Finaled | 10/12/2022 | GRANT WOODS |
Permit Application Clearance Information
| Specific Plan | Cleared | 1/27/2022 | IRA BROWN |
| Coastal Zone | Cleared | 2/3/2022 | DANIEL CORONADO |
| DAS Clearance | Cleared | 2/8/2022 | SHINE LIN |
Contact Information
| Architect | Browning,, Caitlyn Victoria; Lic. No.: C37231 | 2619 ALVIRA ST APT 1 LOS ANGELES, CA 90034 |
| Contractor | Ferrante Koberling Construction Inc; Lic. No.: 988562-B | 2360 EASTMAN AVENUE 112 OXNARD, CA 93030 |
| Engineer | Chen,, Jeff Y; Lic. No.: S4699 | 17500 REDHILL AVENUE SUITE 240 IRVINE, CA 92614 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/29/2022 | Corrections Issued | JOHN DODGE |
| Excavation/Setback/Form/Re-Bar | 5/3/2022 | Partial Approval | NICK LAROCCA |
| Excavation/Setback/Form/Re-Bar | 5/13/2022 | Conditional Approval | JOHN DODGE |
| Excavation/Setback/Form/Re-Bar | 5/31/2022 | Conditional Approval | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 6/1/2022 | Partial Approval | ALAN NOVAK |
| Deputy Steel/Welding | 6/29/2022 | Conditional Approval | ALAN NOVAK |
| Deputy Steel/Welding | 6/30/2022 | Conditional Approval | ALAN NOVAK |
| Excavation/Setback/Form/Re-Bar | 7/11/2022 | Not Ready for Inspection | GRANT WOODS |
| Deputy Drilled-In Anchors | 7/14/2022 | Approved | NICK LAROCCA |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2022 | Partial Approval | SORIN CIRSTOIU |
| Deputy Steel/Welding | 7/22/2022 | Approved | SORIN CIRSTOIU |
| Interior/Exterior Lathing | 8/1/2022 | Approved | SORIN CIRSTOIU |
| Wood Frame | 8/4/2022 | Not Ready for Inspection | NICK LAROCCA |
| METHANE-Rough | 8/12/2022 | Approved | SORIN CIRSTOIU |
| Wood Frame | 8/12/2022 | Approved | SORIN CIRSTOIU |
| Insulation | 8/15/2022 | Partial Approval | SORIN CIRSTOIU |
| Drywall Nailing | 8/16/2022 | Partial Inspection | GRANT WOODS |
| Final | 10/11/2022 | Not Ready for Inspection | GRANT WOODS |
| Drywall Nailing | 10/12/2022 | Approved | GRANT WOODS |
| Final | 10/12/2022 | Permit Finaled | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 10/12/2022 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 10/12/2022 | Approved | GRANT WOODS |
| Structural Steel Frame | 10/12/2022 | Approved | GRANT WOODS |