359 N KILKEA DR 90048

Certificate Information: 359 N KILKEA DR 90048

Application / Permit
21016-30000-56451
Plan Check / Job No.
B21WL05325
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED 1-CAR GARAGE INTO ACCESSORY DWELLINIG UNIT (ADU) PER GCS 65852.2(e)(1)(A) AND WOOD FRAME PRESCRIPTIVE PROVISIONS (WFPP).
Permit Issued
Issued on 4/16/2022
Issuing Office
Current Status
CofO Issued on 10/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/3/2021 APPLICANT
Assigned to Plan Check Engineer 12/6/2021 SERGIO SILVA
Corrections Issued 12/6/2021 SERGIO SILVA
Applicant returned to address corrections 1/24/2022 JASON JANGADA
Applicant returned to address corrections 2/17/2022 JASON JANGADA
Plan Check Approved 3/1/2022 JASON JANGADA
Building Plans Picked Up 3/15/2022 APPLICANT
Issued 4/16/2022 APPLICANT
CofO in Progress 9/28/2022 MICHAEL LEWIS
Permit Finaled 10/15/2022 DEROLD HAUFF
CofO Issued 10/15/2022 DEROLD HAUFF
Permit Finaled 10/15/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/17/2021 JOSE HERNANDEZ
Sewer availability Cleared 12/17/2021 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 12/28/2021 JOSE HERNANDEZ
Construction near power lines Cleared 12/30/2021 WALTER RAMIREZ
Construction within easement Cleared 12/30/2021 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/14/2022 Approved RYAN SALAZAR
PLUMBING-Rough 6/14/2022 Partial Approval RYAN SALAZAR
Deputy Drilled-In Anchors 6/15/2022 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 7/6/2022 Approved ADAM ESCOTO
PLUMBING-Rough 7/6/2022 Corrections Issued ADAM ESCOTO
Shower Pan 7/6/2022 Approved ADAM ESCOTO
HVAC-Rough 7/8/2022 Approved ADAM ESCOTO
PLUMBING-Rough 7/8/2022 Approved ADAM ESCOTO
BUILDING-Rough-Frame 7/12/2022 Partial Approval JEFFREY MEAD
Green Building Rough 7/12/2022 Partial Approval JEFFREY MEAD
METHANE-Rough 7/12/2022 Partial Approval JEFFREY MEAD
Insulation 7/15/2022 Approved ADAM ESCOTO
Interior/Exterior Lathing 7/15/2022 Approved ADAM ESCOTO
Drywall Nailing 7/19/2022 Approved JOSEPH MCGARRY
Green Building Rough 7/19/2022 Approved JOSEPH MCGARRY
Gas Test 7/25/2022 Partial Approval JOSEPH MCGARRY
Sewer 7/25/2022 Partial Approval JOSEPH MCGARRY
Underground Mechanical 7/25/2022 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 8/4/2022 Partial Inspection MICHAEL LEWIS
Sewer 8/26/2022 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 9/7/2022 Approved MICHAEL LEWIS
Final 9/7/2022 Corrections Issued MICHAEL LEWIS
Green Building Final 9/7/2022 Corrections Issued MICHAEL LEWIS
METHANE-Final 9/7/2022 Approved MICHAEL LEWIS
METHANE-Rough 9/7/2022 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 9/7/2022 SGSOV Approved MICHAEL LEWIS
Smoke Detectors 9/7/2022 Approved MICHAEL LEWIS
Final 9/27/2022 OK to Issue CofO MICHAEL LEWIS
Green Building Final 9/27/2022 Approved MICHAEL LEWIS