2707 S MIDVALE AVE 90064

Certificate Information: 2707 S MIDVALE AVE 90064

Application / Permit
21016-30000-56432
Plan Check / Job No.
B21WL05319
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Kitchen Remodel in an (E) 1-Story S.F.D
Permit Issued
Issued on 1/24/2022
Issuing Office
Current Status
Permit Finaled on 8/26/2022

Permit Application Status History

Submitted 12/3/2021 APPLICANT
Assigned to Plan Check Engineer 12/6/2021 DAVID CASTILLO
Corrections Issued 12/6/2021 DAVID CASTILLO
Plan Check Approved 12/27/2021 RICHARD GARCIA
Building Plans Picked Up 12/28/2021 APPLICANT
Issued 1/24/2022 APPLICANT
Permit Finaled 8/25/2022 JOHNNY MIRANDA

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/16/2021 SERGIO VALENZUELA

Contact Information

Contractor Luxe Remodeling; Lic. No.: 993473-B 329 N WETHERLY DRIVE #205      BEVERLY HILLS, CA 90211
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22121 CLARENDON ST APT 340      WOODLAND HILLS, CA 91367

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/27/2022 Corrections Issued OGANES TARAKHCHYAN
BUILDING-Rough-Frame 1/28/2022 Not Ready for Inspection STEPHANIE SWANSON
FLOOD-Proofing Certificate 1/28/2022 Approved STEPHANIE SWANSON
Footing/Foundation/Slab 1/28/2022 Corrections Issued STEPHANIE SWANSON
MERV13>=Rough 1/28/2022 Approved STEPHANIE SWANSON
Wood Frame 1/28/2022 Not Ready for Inspection STEPHANIE SWANSON
Footing/Foundation/Slab 2/3/2022 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 2/17/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 2/28/2022 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 3/22/2022 Approved JOHNNY MIRANDA
HVAC-Rough 3/22/2022 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 3/22/2022 Approved JOHNNY MIRANDA
Insulation 3/24/2022 Corrections Issued OGANES TARAKHCHYAN
BUILDING-Rough-Frame 4/1/2022 No Access for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 4/1/2022 No Access for Inspection OGANES TARAKHCHYAN
HVAC-Rough 4/1/2022 No Access for Inspection OGANES TARAKHCHYAN
Insulation 4/1/2022 No Access for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 4/1/2022 No Access for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 4/5/2022 Approved OGANES TARAKHCHYAN
HVAC-Rough 4/5/2022 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 4/5/2022 Approved OGANES TARAKHCHYAN
Drywall Nailing 4/7/2022 Approved EVAN COOPER
BUILDING-Rough-Frame 6/9/2022 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 6/9/2022 SGSOV Not Ready JOHNNY MIRANDA
ELECTRICAL-Final 6/13/2022 Approved JOHNNY MIRANDA
PLUMBING-Final 6/13/2022 Corrections Issued JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 6/24/2022 SGSOV Not Ready JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 7/18/2022 SGSOV Not Ready JOHNNY MIRANDA
Final 7/25/2022 Corrections Issued JOHNNY MIRANDA
MERV13>=Final 7/25/2022 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 7/25/2022 SGSOV Not Ready JOHNNY MIRANDA
Smoke Detectors 7/25/2022 Approved JOHNNY MIRANDA
Final 8/25/2022 Permit Finaled JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 8/25/2022 SGSOV Approved JOHNNY MIRANDA