838-840 N HANLEY AVE 90049
Certificate Information: 838-840 N HANLEY AVE 90049
- Application / Permit
- 21016-30000-55387
- Plan Check / Job No.
- B21WL05182
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- convert existing carport to JADU per 65852.2(e)(1)(A) and 65852.22 convert existing laundry to bathroom and relocate laundry
- Permit Issued
- Issued on 5/31/2022
- Issuing Office
- Current Status
- CofO Issued on 9/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/3/2021 | KHUONG TRUONG |
| Corrections Issued | 12/4/2021 | KHUONG TRUONG |
| Applicant returned to address corrections | 3/30/2022 | EDWIN ESPIN |
| Building Plans Picked Up | 4/1/2022 | APPLICANT |
| Applicant returned to address corrections | 4/16/2022 | EDWIN ESPIN |
| Applicant returned to address corrections | 5/3/2022 | JASON JANGADA |
| Applicant returned to address corrections | 5/9/2022 | FERNANDO FLORES |
| Plan Check Approved | 5/31/2022 | KHUONG TRUONG |
| Issued | 5/31/2022 | APPLICANT |
| CofO in Progress | 9/12/2023 | ARAM AVEDISIAN |
| Permit Finaled | 9/30/2024 | RICHARD STEINBACH |
| CofO Issued | 9/30/2024 | RICHARD STEINBACH |
| Permit Finaled | 9/30/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| ZA Case | Cleared | 1/27/2022 | ANACANY HURTADO |
| Construction near power lines | Cleared | 2/16/2022 | RIDWAN HARDY |
| Address approval | Cleared | 2/18/2022 | TRACY TATE |
| Sewer availability | Cleared | 2/18/2022 | TRACY TATE |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2022 | TRACY TATE |
| Grading Pre-Inspection | Cleared | 3/30/2022 | EDWIN ESPIN |
Contact Information
| Contractor | Soumekh Michael N; Lic. No.: 773770-B | 1140 SOUTH ALFRED STREET LOS ANGELES, CA 90035 |
| Engineer | Nohroodi,, Nader Gholi; Lic. No.: C36971 | 7389 PERIGORD CT TUJUNGA, CA 91042 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/20/2022 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 10/19/2022 | Approved | JUAN VALENZUELA |
| Shower Pan | 10/19/2022 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 11/1/2022 | Conditional Approval | ANDREW NAVE |
| ELECTRICAL-Rough | 11/1/2022 | Approved | ANDREW NAVE |
| HVAC-Rough | 11/1/2022 | Approved | ANDREW NAVE |
| Insulation | 11/1/2022 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 11/1/2022 | Partial Approval | ANDREW NAVE |
| Special/Order Compliance | 11/1/2022 | Corrections Issued | ANDREW NAVE |
| BUILDING-Rough-Frame | 11/7/2022 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 11/10/2022 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 1/31/2023 | SGSOV Not Ready | KEVIN SARGSYAN |
| Final | 3/15/2023 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 3/15/2023 | SGSOV Not Ready | KEVIN SARGSYAN |
| Smoke Detectors | 3/15/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Final | 9/12/2023 | OK to Issue CofO | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 9/12/2023 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 9/12/2023 | Approved | ARAM AVEDISIAN |