6725 W COLGATE AVE 90048

Certificate Information: 6725 W COLGATE AVE 90048

Application / Permit
21016-30000-55346
Plan Check / Job No.
B21WL05168
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Garage conversion to ADU. PER GCS65852.2(e)(1)(A)
Permit Issued
Issued on 7/11/2022
Issuing Office
Current Status
CofO Issued on 8/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/23/2021 APPLICANT
Assigned to Plan Check Engineer 11/24/2021 RICHARD GARCIA
Corrections Issued 11/28/2021 RICHARD GARCIA
Applicant returned to address corrections 1/15/2022 RICHARD GARCIA
Applicant returned to address corrections 4/2/2022 RICHARD GARCIA
Applicant returned to address corrections 5/3/2022 ALFREDO JARA
Plan Check Approved 5/10/2022 ALFREDO JARA
Issued 7/11/2022 APPLICANT
Building Plans Picked Up 7/13/2022 APPLICANT
CofO in Progress 8/2/2023 ARAM AVEDISIAN
Permit Finaled 8/10/2023 DANIEL ORRANTE
CofO Issued 8/10/2023 DANIEL ORRANTE
Permit Finaled 8/10/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/28/2022 TREVOR QUAN
Roof/Waste drainage to street Cleared 1/28/2022 TREVOR QUAN
Sewer availability Cleared 1/28/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 1/31/2022 TREVOR QUAN
Construction near power lines Cleared 3/19/2022 RIDWAN HARDY
Construction within easement Cleared 3/19/2022 RIDWAN HARDY
ZI Cleared 3/23/2022 RUBEN VASQUEZ

Contact Information

Contractor West Coast Construction Management Supervisors, Inc; Lic. No.: 969801-B 22099 ALTA DR      TOPANGA, CA 90290
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVENUE      LONG BEACH, CA 90813

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/25/2022 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 8/9/2022 Partial Approval EVAN COOPER
Deputy Drilled-In Anchors 9/22/2022 Conditional Approval EVAN COOPER
Footing/Foundation/Slab 9/26/2022 Not Ready for Inspection EVAN COOPER
Excavation/Setback/Form/Re-Bar 9/29/2022 Partial Approval EVAN COOPER
Footing/Foundation/Slab 10/24/2022 Approved EVAN COOPER
PLUMBING-Rough 10/24/2022 Partial Approval EVAN COOPER
ELECTRICAL-Rough 12/2/2022 Corrections Issued EVAN COOPER
PLUMBING-Rough 12/2/2022 Corrections Issued EVAN COOPER
Special/Order Compliance 12/2/2022 Partial Inspection JEREMY TODD
Deputy Wood Construction 12/14/2022 Conditional Approval JEREMY TODD
BUILDING-Rough-Frame 1/13/2023 Partial Approval JEREMY TODD
ELECTRICAL-Rough 1/13/2023 Partial Approval JEREMY TODD
Interior/Exterior Lathing 1/13/2023 Approved JEREMY TODD
METHANE-Rough 1/13/2023 Partial Approval JEREMY TODD
PLUMBING-Rough 1/13/2023 Partial Approval JEREMY TODD
BUILDING-Rough-Frame 2/9/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 2/9/2023 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 2/9/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Insulation 2/9/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
METHANE-Rough 2/9/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 2/9/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 2/24/2023 Conditional Approval JEREMY TODD
METHANE-Rough 2/24/2023 Approved JEREMY TODD
Shower Pan 2/24/2023 Not Ready for Inspection JEREMY TODD
Shower Pan 3/6/2023 Approved JESUS PINEDA
Drywall Nailing 3/13/2023 Approved JEREMY TODD
Interior/Exterior Lathing 3/13/2023 Approved JEREMY TODD
BUILDING-Rough-Frame 7/28/2023 Approved ARAM AVEDISIAN
Final 7/28/2023 Corrections Issued ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 7/28/2023 SGSOV Not Required ARAM AVEDISIAN
Smoke Detectors 7/28/2023 Approved ARAM AVEDISIAN
ELECTRICAL-Final 8/2/2023 Approved ARAM AVEDISIAN
Final 8/2/2023 OK to Issue CofO ARAM AVEDISIAN
HVAC-Final 8/2/2023 Approved ARAM AVEDISIAN
PLUMBING-Final 8/2/2023 Approved ARAM AVEDISIAN