4325 S LYCEUM AVE 90066
Certificate Information: 4325 S LYCEUM AVE 90066
- Application / Permit
- 21016-30000-54803
- Plan Check / Job No.
- B21WL05082
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- convert garage to ADU per CA Govt. Code 65852.2(e)(1)(A). Construction per WFPP
- Permit Issued
- Issued on 4/4/2022
- Issuing Office
- Current Status
- CofO Issued on 1/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2021 | KAVIAN REFAHI |
| Corrections Issued | 11/28/2021 | KAVIAN REFAHI |
| Applicant returned to address corrections | 1/12/2022 | EDWIN ESPIN |
| Plan Check Approved | 2/25/2022 | KAVIAN REFAHI |
| Issued | 4/4/2022 | APPLICANT |
| Building Plans Picked Up | 5/2/2022 | APPLICANT |
| CofO in Progress | 1/3/2023 | JESUS RODRIGUEZ |
| Permit Finaled | 1/18/2023 | DANIEL ORRANTE |
| CofO Issued | 1/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 1/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/28/2022 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 1/28/2022 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2022 | JOSE HERNANDEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/16/2022 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 8/18/2022 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 8/18/2022 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 10/6/2022 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Rough | 10/6/2022 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 10/6/2022 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 10/12/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2022 | Partial Approval | JESUS RODRIGUEZ |
| HVAC-Final | 10/12/2022 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Rough | 10/12/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 10/12/2022 | Approved | JESUS RODRIGUEZ |
| Sewer | 10/12/2022 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 10/12/2022 | Corrections Issued | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 10/18/2022 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2022 | Approved | ANDREW NAVE |
| Insulation | 10/18/2022 | Partial Approval | ANDREW NAVE |
| Interior/Exterior Lathing | 10/18/2022 | Partial Approval | ANDREW NAVE |
| Insulation | 10/24/2022 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 10/24/2022 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 10/27/2022 | Conditional Approval | CLAYTON GRAHAM |
| Drywall Nailing | 12/21/2022 | Approved | JESUS RODRIGUEZ |
| Final | 12/21/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 12/21/2022 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 12/21/2022 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 12/21/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 12/29/2022 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 12/29/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 12/29/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 12/29/2022 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 12/29/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 1/3/2023 | Approved | JESUS RODRIGUEZ |
| Final | 1/3/2023 | OK to Issue CofO | JESUS RODRIGUEZ |
| Green Building Final | 1/3/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 1/3/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 1/3/2023 | Approved | JESUS RODRIGUEZ |