5009 N MURIETTA AVE 91423

Certificate Information: 5009 N MURIETTA AVE 91423

Application / Permit
21016-30000-54802
Plan Check / Job No.
B21WL05079
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (e) det. 2-car garage to and ADU (365 sf) PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 7/13/2022
Issuing Office
Current Status
CofO Issued on 1/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/18/2021 APPLICANT
Assigned to Plan Check Engineer 12/9/2021 REZA HAGHIGHAT
Corrections Issued 12/13/2021 REZA HAGHIGHAT
Quality Review Completed 12/22/2021 TARIK SAOUD
Plan Check Approved 5/12/2022 REZA HAGHIGHAT
Issued 7/13/2022 APPLICANT
Building Plans Picked Up 7/20/2022 APPLICANT
CofO in Progress 12/13/2023 MISAEL ESPARZA
Permit Finaled 1/31/2024 RUBEN SALAS
CofO Issued 1/31/2024 RUBEN SALAS
Permit Finaled 1/31/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/22/2022 CARLOS AGUILERA
Sewer availability Cleared 2/22/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/23/2022 CARLOS AGUILERA
ZI Cleared 2/23/2022 RICHARD REASER
Hydrant and Access approval Cleared 3/28/2022 DWIGHT SANKEY
Construction near power lines Cleared 4/19/2022 RIDWAN HARDY

Contact Information

Contractor Copper Construction Llc; Lic. No.: 1060557-B 605 S MILLIKEN AVENUE UNIT D      ONTARIO, CA 91761
Engineer Chen,, Junfei; Lic. No.: C85841 726 FAMILY TREE      IRVINE, CA 92618

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/13/2022 Corrections Issued CALEB MEISTER
Sewer 10/25/2022 Approved MISAEL ESPARZA
Underground Mechanical 10/28/2022 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/8/2023 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 3/29/2023 Partial Approval MISAEL ESPARZA
ELECTRICAL-Rough 5/1/2023 Approved MISAEL ESPARZA
PLUMBING-Rough 5/1/2023 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 5/8/2023 Corrections Issued MISAEL ESPARZA
Green Building Rough 5/8/2023 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 5/8/2023 Corrections Issued MISAEL ESPARZA
Insulation 5/8/2023 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 5/8/2023 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 5/15/2023 Conditional Approval ROBERT GOLD
Deputy Wood Construction 5/15/2023 Conditional Approval MICHAEL SMITH
Green Building Rough 5/15/2023 Partial Inspection ROBERT GOLD
HVAC-Rough 5/15/2023 Approved ROBERT GOLD
Deputy Wood Construction 5/16/2023 Conditional Approval MICHAEL SMITH
Underground Mechanical 5/26/2023 Partial Approval JOHN COLEMAN
BUILDING-Rough-Frame 7/13/2023 Approved JUAN VALENZUELA
Green Building Rough 7/13/2023 Approved JUAN VALENZUELA
Insulation 7/13/2023 Approved JUAN VALENZUELA
Verify Sprinkler Sign Off 7/13/2023 Approved JUAN VALENZUELA
Drywall Nailing 7/25/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 7/25/2023 Approved MISAEL ESPARZA
Shower Pan 8/10/2023 Approved MISAEL ESPARZA
ELECTRICAL-Final 10/4/2023 Not Ready for Inspection MISAEL ESPARZA
Final 10/17/2023 Corrections Issued MISAEL ESPARZA
Green Building Final 10/17/2023 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 10/17/2023 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 10/17/2023 Corrections Issued MISAEL ESPARZA
Final 12/5/2023 Corrections Issued MISAEL ESPARZA
Green Building Final 12/5/2023 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 12/5/2023 Approved MISAEL ESPARZA
Final 12/11/2023 OK to Issue CofO MISAEL ESPARZA
Green Building Final 12/11/2023 Approved MISAEL ESPARZA