1357 N HIGHLAND AVE 90028
Certificate Information: 1357 N HIGHLAND AVE 90028
- Application / Permit
- 21016-30000-54755
- Plan Check / Job No.
- B21WL05075
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (4) Art Gallery
- Work Description
- Interior T.I. of existing 3 story commercial building with structural alterations and change of use from yoga studio, takeout restaurant, retail and office to art gallery and office. No exterior work.
- Permit Issued
- Issued on 5/23/2022
- Issuing Office
- Current Status
- CofO Issued on 12/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/18/2021 | APPLICANT |
| Corrections Issued | 11/28/2021 | JAHANSHAH POURHASSAN |
| Assigned to Plan Check Engineer | 12/2/2021 | JAHANSHAH POURHASSAN |
| Corrections Issued | 12/9/2021 | JAHANSHAH POURHASSAN |
| Disabled Access Plans Picked Up | 12/9/2021 | APPLICANT |
| Quality Review Completed | 1/4/2022 | TARIK SAOUD |
| Applicant returned to address corrections | 2/2/2022 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 2/9/2022 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 2/16/2022 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 2/18/2022 | JAHANSHAH POURHASSAN |
| Green Plans Picked Up | 3/2/2022 | APPLICANT |
| Applicant returned to address corrections | 3/14/2022 | JAHANSHAH POURHASSAN |
| Building Plans Picked Up | 3/17/2022 | APPLICANT |
| Plan Check Approved | 5/23/2022 | JAHANSHAH POURHASSAN |
| Issued | 5/23/2022 | APPLICANT |
| TCO Issued (Expire Date: 03-21-2023) | 9/22/2022 | TED RIES |
| CofO in Progress | 12/19/2022 | TED RIES |
| Permit Finaled | 12/19/2022 | TED RIES |
| CofO Issued | 12/19/2022 | TED RIES |
| Permit Finaled | 12/19/2022 | TED RIES |
Permit Application Clearance Information
| ZA Case | Cleared | 1/11/2022 | RUBEN VASQUEZ |
| Redevelopment Project Area | Cleared | 1/21/2022 | GRACIELA ACOSTA |
| DAS Clearance | Cleared | 3/31/2022 | SHINE LIN |
| Green Code | Cleared | 4/22/2022 | RICHARD GARCIA |
Contact Information
| Architect | Chung,, Hye-Young; Lic. No.: C35186 | 12721 RUBENS AVENUE LOS ANGELES, CA 90066 |
| Contractor | Gundry Partners Lp; Lic. No.: 1006248-B | 17434 BELLFLOWER BLVD SUITE 300 BELLFLOWER, CA 90706 |
| Engineer | Ibarra,, Marco A; Lic. No.: C74010 | 16 N MARENGON AVE STE 604 PASADENA, CA 91101 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/27/2022 | Partial Approval | JONATHAN QUACH |
| Pre-Inspection | 5/27/2022 | Approved | JONATHAN QUACH |
| Green Building Rough | 5/31/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Wood Frame | 5/31/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 6/3/2022 | Partial Approval | JONATHAN QUACH |
| Insulation | 6/6/2022 | Approved | JONATHAN QUACH |
| Interior/Exterior Lathing | 6/21/2022 | Partial Approval | JONATHAN QUACH |
| Green Building Rough | 6/24/2022 | Not Ready for Inspection | DAVID BURKHEAD |
| Light Gage Steel Frame | 6/24/2022 | Partial Approval | DAVID BURKHEAD |
| Drywall Nailing | 6/28/2022 | Partial Approval | DAVID BURKHEAD |
| Insulation | 6/28/2022 | Partial Approval | DAVID BURKHEAD |
| Drywall Nailing | 7/15/2022 | Partial Approval | JONATHAN QUACH |
| Light Gage Steel Frame | 7/29/2022 | Not Ready for Inspection | JONATHAN QUACH |
| Light Gage Steel Frame | 8/2/2022 | Approved | JONATHAN QUACH |
| Drywall Nailing | 8/11/2022 | Partial Approval | DAVID BURKHEAD |
| Drywall Nailing | 8/16/2022 | Approved | DAVID BURKHEAD |
| Pre-Inspection | 9/13/2022 | Approved | JONATHAN QUACH |
| Final | 9/14/2022 | No Access for Inspection | JONATHAN QUACH |
| Green Building Final | 9/14/2022 | Approved | JONATHAN QUACH |
| Green Building Rough | 9/14/2022 | Approved | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 9/14/2022 | SGSOV Approved | JONATHAN QUACH |
| Smoke Detectors | 9/14/2022 | Approved | JONATHAN QUACH |
| Wood Frame | 9/14/2022 | Not Ready for Inspection | JONATHAN QUACH |
| Pre-Inspection | 9/15/2022 | Approved | TED RIES |
| Final | 9/19/2022 | Conditional Approval | TED RIES |
| Wood Frame | 9/19/2022 | Approved | TED RIES |
| Final | 11/10/2022 | OK to Issue CofO | JONATHAN QUACH |