17599 W CANTARA ST 91325
Certificate Information: 17599 W CANTARA ST 91325
- Application / Permit
- 21016-30000-53516
- Plan Check / Job No.
- B21WL04998
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) ADU conversion from an (E) Detached garage Per WFPP and per GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 4/29/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2021 | KHUONG TRUONG |
| Corrections Issued | 11/27/2021 | KHUONG TRUONG |
| Building Plans Picked Up | 2/23/2022 | APPLICANT |
| Applicant returned to address corrections | 4/27/2022 | ZAW HAN |
| Plan Check Approved | 4/28/2022 | RICHARD GARCIA |
| Issued | 4/29/2022 | APPLICANT |
| CofO in Progress | 4/17/2023 | RAUL OLAGI |
| CofO Issued | 4/18/2023 | MICHAEL SMITH |
| Permit Finaled | 4/18/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/14/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 1/14/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2022 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 4/27/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/3/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 5/3/2022 | Partial Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/16/2022 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 5/16/2022 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 5/16/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 5/16/2022 | Corrections Issued | RAUL OLAGI |
| Shower Pan | 5/16/2022 | Not Ready for Inspection | RAUL OLAGI |
| ELECTRICAL-Rough | 5/17/2022 | Corrections Issued | MICHAEL TEMPLE |
| HVAC-Rough | 5/17/2022 | Approved | MICHAEL TEMPLE |
| PLUMBING-Rough | 5/17/2022 | Approved | MICHAEL TEMPLE |
| Special/Order Compliance | 5/17/2022 | Partial Inspection | MICHAEL TEMPLE |
| Insulation | 5/18/2022 | Partial Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/20/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 5/20/2022 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 5/20/2022 | Approved | RAUL OLAGI |
| Insulation | 5/20/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 5/20/2022 | Partial Approval | RAUL OLAGI |
| Drywall Nailing | 5/25/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 6/1/2022 | Approved | DEANDRE HOFFMAN |
| ELECTRICAL-Rough | 6/2/2022 | Partial Approval | JOHN HAYES |
| Gas Test | 6/2/2022 | Approved | JOHN HAYES |
| Sewer | 6/2/2022 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 6/16/2022 | Corrections Issued | DEANDRE HOFFMAN |
| Final | 6/16/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Green Building Final | 6/16/2022 | Corrections Issued | DEANDRE HOFFMAN |
| HVAC-Final | 6/16/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| PLUMBING-Final | 6/16/2022 | Approved | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 6/16/2022 | SGSOV Not Ready | DEANDRE HOFFMAN |
| Smoke Detectors | 6/16/2022 | Approved | DEANDRE HOFFMAN |
| ELECTRICAL-Final | 6/22/2022 | Approved | ALAN MORELOS |
| Final | 6/22/2022 | Not Ready for Inspection | ALAN MORELOS |
| Green Building Final | 6/22/2022 | Approved | ALAN MORELOS |
| HVAC-Final | 6/22/2022 | Approved | ALAN MORELOS |
| SGSOV-Seismic Gas S/O Valve | 6/22/2022 | SGSOV Approved | ALAN MORELOS |
| Service/Power Release | 6/22/2022 | Not Ready for Inspection | ALAN MORELOS |
| Final | 4/17/2023 | OK to Issue CofO | RAUL OLAGI |