1608 N CAHUENGA BLVD 90028

Certificate Information: 1608 N CAHUENGA BLVD 90028

Application / Permit
21016-30000-52976
Plan Check / Job No.
B21WL04948
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
REMOVE AND RELOCATE BAR, REMODEL KITCHEN AND ADD WALL AND DOORS TO SEPARATE BAR FROM KITCHEN, REVISE THE FRONT FACAD, INSTALL NEW STEEL LIQUOR RACK HUNG FROM THE CEILING AROUND THE ENTIRE BAR.
Permit Issued
Issued on 7/27/2022
Issuing Office
Valley
Current Status
Permit Finaled on 1/17/2024

Permit Application Status History

Submitted 11/10/2021 APPLICANT
Assigned to Plan Check Engineer 11/12/2021 JAHANSHAH POURHASSAN
Corrections Issued 11/14/2021 JAHANSHAH POURHASSAN
Building Plans Picked Up 11/23/2021 APPLICANT
Applicant returned to address corrections 3/12/2022 JAHANSHAH POURHASSAN
Applicant returned to address corrections 3/16/2022 JAHANSHAH POURHASSAN
Applicant returned to address corrections 3/28/2022 JAHANSHAH POURHASSAN
Applicant returned to address corrections 4/29/2022 RICHARD GARCIA
Plan Check Approved 7/13/2022 RICHARD GARCIA
Issued 7/27/2022 APPLICANT
Permit Finaled 1/16/2024 RONALD JIMENEZ

Permit Application Clearance Information

Redevelopment Project Area Cleared 1/31/2022 DAVID URITA
Food establishment approval Cleared 5/10/2022 LACDHS APPROVED
"D" conditions Cleared 5/31/2022 JASON CHAN
ZA Case Cleared 6/1/2022 ANACANY HURTADO
ZA Case Cleared 6/1/2022 ANACANY HURTADO
ZI Cleared 6/1/2022 ANACANY HURTADO
ZI Cleared 6/1/2022 ANACANY HURTADO
Food Service Establishment Cleared 6/21/2022 KENNETH BROWNE

Contact Information

Architect Randall,, Donald Bruce; Lic. No.: C10350 650 N WESTBOURNE DRIVE # 109      WEST HOLLYWOOD, CA 90069
Contractor Owner-Builder       ,
Engineer Mohammadi,, Saeid; Lic. No.: C82330 17412 VENTUTRA BLVD 21      ENCINO, CA 91316

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/27/2022 Not Ready for Inspection JONATHAN QUACH
Pre-Inspection 9/27/2022 Not Ready for Inspection JONATHAN QUACH
Deputy Drilled-In Anchors 9/28/2022 Conditional Approval MICHAEL ROSENBERG
Wood Frame 10/20/2022 Partial Inspection JONATHAN QUACH
Deputy Steel/Welding 11/15/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 11/17/2022 Conditional Approval MICHAEL ROSENBERG
Wood Frame 11/18/2022 Partial Approval GREGORY POMISH
Drywall Nailing 12/6/2022 Partial Approval JONATHAN QUACH
Final 12/20/2023 Not Ready for Inspection RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 12/20/2023 SGSOV Approved RONALD JIMENEZ
Smoke Detectors 12/20/2023 Approved RONALD JIMENEZ
Final 1/16/2024 Permit Finaled RONALD JIMENEZ