935 3/4 W 79TH ST 90044

Certificate Information: 935 3/4 W 79TH ST 90044

Application / Permit
21016-30000-49639
Plan Check / Job No.
B21WL04825
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of (E) Detached garage into ADU PER GCS 65852.2(e)(1)(A). Per engineering design.
Permit Issued
Issued on 2/18/2022
Issuing Office
Current Status
CofO Issued on 3/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/3/2021 APPLICANT
Assigned to Plan Check Engineer 11/5/2021 ALFREDO JARA
Corrections Issued 11/8/2021 ALFREDO JARA
Applicant returned to address corrections 12/21/2021 ALFREDO JARA
Plan Check Approved 12/22/2021 ALFREDO JARA
Building Plans Picked Up 12/27/2021 APPLICANT
Issued 2/18/2022 APPLICANT
CofO in Progress 2/28/2025 MICHAEL LEWIS
Permit Finaled 3/2/2025 DEROLD HAUFF
CofO Issued 3/2/2025 DEROLD HAUFF
Permit Finaled 3/2/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/30/2021 KHOUNG LE
Roof/Waste drainage to street Cleared 11/30/2021 KHOUNG LE
Sewer availability Cleared 11/30/2021 KHOUNG LE
Eng Process Fee Ord 176,300 Cleared 12/6/2021 KHOUNG LE

Contact Information

Contractor Owner-Builder       ,
Engineer Mah,, Edwin Poy-Dor; Lic. No.: C27141 1740 APPIAN WAY      MONTEBELLO, CA 90640

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/26/2022 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 3/19/2024 Approved MICHAEL LEWIS
Green Building Rough 3/19/2024 Approved MICHAEL LEWIS
Drywall Nailing 2/27/2025 Approved MICHAEL LEWIS
Final 2/27/2025 OK to Issue CofO MICHAEL LEWIS
Green Building Final 2/27/2025 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 2/27/2025 SGSOV Not Required MICHAEL LEWIS
Smoke Detectors 2/27/2025 Approved MICHAEL LEWIS