3800 S MENTONE AVE 90232

Certificate Information: 3800 S MENTONE AVE 90232

Application / Permit
21016-30000-48347
Plan Check / Job No.
B21WL04813
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(1) Accessory Dwelling Unit
Work Description
Interior conversion of non-livable space to 2 ADUs
Permit Issued
Issued on 8/7/2023
Issuing Office
Current Status
CofO Issued on 1/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/2/2021 APPLICANT
Assigned to Plan Check Engineer 11/10/2021 FELIPE HERNANDEZ
Corrections Issued 11/18/2021 FELIPE HERNANDEZ
Disabled Access Plans Picked Up 11/22/2021 APPLICANT
Quality Review Completed 11/29/2021 TARIK SAOUD
Building Plans Picked Up 12/1/2021 APPLICANT
Green Plans Picked Up 3/17/2022 APPLICANT
Applicant returned to address corrections 11/1/2022 HOOMAN HAJIZADEH
Plan Check Approved 8/7/2023 HOOMAN HAJIZADEH
Issued 8/7/2023 APPLICANT
CofO in Progress 1/30/2024 FARHAD DADBIN
Permit Finaled 1/31/2024 DAVID TSAU
CofO Issued 1/31/2024 DAVID TSAU
Permit Finaled 1/31/2024 DAVID TSAU

Permit Application Clearance Information

Address approval Cleared 12/3/2021 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 12/3/2021 SAUL GARCIA
Sewer availability Cleared 12/3/2021 SAUL GARCIA
Green Code Cleared 3/10/2022 RICHARD GARCIA
DAS Clearance Cleared 4/14/2022 SHINE LIN
Tenant Habitability Plan Cleared 11/3/2022 RICARDO BOHORQUEZ
ZA Case Cleared 11/3/2022 RYAN LY
ZA Case Cleared 11/3/2022 RYAN LY
ZA Case Cleared 11/3/2022 RYAN LY
SB8 RUD Cleared 1/26/2023 JESSICA WANG
Fire Marshal Fire Life Safety Cleared 7/18/2023 DOMINIQUE MEDINA

Contact Information

Architect Zbikowski,, Jeffrey; Lic. No.: C35389 4043 IRVING PL SUITE B      CULVER CITY, CA 90232
Contractor Owner-Builder       ,

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Insulation 8/9/2023 Not Ready for Inspection FARHAD DADBIN
Insulation 8/15/2023 Corrections Issued FARHAD DADBIN
Final 12/7/2023 Not Ready for Inspection FARHAD DADBIN
Green Building Final 12/7/2023 Approved FARHAD DADBIN
Green Building Rough 12/7/2023 Approved FARHAD DADBIN
METHANE-Final 12/7/2023 Approved FARHAD DADBIN
METHANE-Rough 12/7/2023 Approved FARHAD DADBIN
Reinforced Concrete Frame 12/7/2023 Approved FARHAD DADBIN
Reinforced Masonry Frame 12/7/2023 Approved FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 12/7/2023 SGSOV Approved FARHAD DADBIN
Smoke Detectors 12/7/2023 Not Ready for Inspection FARHAD DADBIN
Final 12/18/2023 Conditional Approval GRANT WOODS
Smoke Detectors 12/18/2023 Approved GRANT WOODS
Final 1/26/2024 OK to Issue CofO FARHAD DADBIN