2504 1/2 S VINEYARD AVE 90016
Certificate Information: 2504 1/2 S VINEYARD AVE 90016
- Application / Permit
- 21016-30000-48181
- Plan Check / Job No.
- B21WL04797
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) Detached garage to ADU. PER GCS 65852.2(e)(1)(A). Per WFPP.
- Permit Issued
- Issued on 11/18/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2021 | KHUONG TRUONG |
| Corrections Issued | 11/15/2021 | KHUONG TRUONG |
| Applicant returned to address corrections | 1/4/2022 | RICHARD GARCIA |
| Building Plans Picked Up | 1/7/2022 | APPLICANT |
| Applicant returned to address corrections | 2/2/2022 | ALFREDO JARA |
| Applicant returned to address corrections | 9/14/2022 | ALFREDO JARA |
| Plan Check Approved | 10/3/2022 | ALFREDO JARA |
| Issued | 11/18/2022 | APPLICANT |
| CofO in Progress | 4/13/2023 | CALEB MEISTER |
| No Progress | 5/25/2023 | CALEB MEISTER |
| CofO in Progress | 7/14/2023 | CALEB MEISTER |
| Permit Finaled | 7/16/2023 | DEROLD HAUFF |
| CofO Issued | 7/16/2023 | DEROLD HAUFF |
| Permit Finaled | 7/16/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/19/2022 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 7/19/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 7/19/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2022 | AMAAN MALIK |
| Tenant Habitability Plan | Cleared | 8/8/2022 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/29/2022 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 11/29/2022 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 11/29/2022 | Approved | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 12/1/2022 | Partial Inspection | BRENDAN MORELLI |
| Underground Mechanical | 12/1/2022 | Partial Inspection | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 12/8/2022 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 12/8/2022 | Approved | STUART CHAPMAN |
| HVAC-Rough | 12/8/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 12/8/2022 | Approved | STUART CHAPMAN |
| Insulation | 12/14/2022 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 12/14/2022 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 12/21/2022 | Approved | CALEB MEISTER |
| Gas Test | 1/10/2023 | Approved | CALEB MEISTER |
| Underground Mechanical | 1/10/2023 | Approved | CALEB MEISTER |
| ELECTRICAL-Final | 1/23/2023 | Approved | CALEB MEISTER |
| HVAC-Final | 1/23/2023 | Corrections Issued | CALEB MEISTER |
| PLUMBING-Final | 1/23/2023 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 2/1/2023 | Approved | CALEB MEISTER |
| Final | 2/1/2023 | Corrections Issued | CALEB MEISTER |
| HVAC-Final | 2/1/2023 | Not Ready for Inspection | CALEB MEISTER |
| MERV13>=Final | 2/1/2023 | Approved | CALEB MEISTER |
| MERV13>=Rough | 2/1/2023 | Approved | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 2/1/2023 | SGSOV Approved | CALEB MEISTER |
| Smoke Detectors | 2/1/2023 | Approved | CALEB MEISTER |
| Final | 4/12/2023 | OK to Issue CofO | CALEB MEISTER |
| HVAC-Final | 4/12/2023 | Approved | CALEB MEISTER |
| Special/Order Compliance | 5/25/2023 | Corrections Issued | CALEB MEISTER |