3246 S FEDERAL AVE 90066
Certificate Information: 3246 S FEDERAL AVE 90066
- Application / Permit
- 21016-30000-38269
- Plan Check / Job No.
- B21WL04521
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel (E) Single family dwelling.. Per engineering design.
- Permit Issued
- Issued on 2/10/2022
- Issuing Office
- Current Status
- Permit Finaled on 7/24/2023
Permit Application Status History
| Submitted | 10/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2021 | ALFREDO JARA |
| Corrections Issued | 10/21/2021 | ALFREDO JARA |
| Plan Check Approved | 11/16/2021 | ALFREDO JARA |
| Issued | 2/10/2022 | APPLICANT |
| Building Plans Picked Up | 2/11/2022 | APPLICANT |
| Permit Finaled | 7/21/2023 | JESUS PINEDA |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/4/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 11/5/2021 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 11/16/2021 | ALFREDO JARA |
Contact Information
| Contractor | X3build Inc; Lic. No.: 1065494-B | 3163 DONALD DOUGLAS LOOP SOUTH SANTA MONICA, CA 90405 |
| Engineer | Ilasin,, John Lacebal; Lic. No.: C67469 | 1011 OARFISH LN OXNARD, CA 93035 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/16/2022 | Approved | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 3/16/2022 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2022 | Partial Approval | JOHNNY MIRANDA |
| HVAC-Rough | 6/20/2022 | Corrections Issued | RICHARD STEINBACH |
| PLUMBING-Rough | 7/11/2022 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 7/28/2022 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 7/28/2022 | Approved | HERBERT GIRON |
| Shower Pan | 7/28/2022 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Rough | 8/1/2022 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 8/1/2022 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/4/2022 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2022 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 8/8/2022 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 8/15/2022 | Partial Approval | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 8/17/2022 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 8/22/2022 | Approved | JOHNNY MIRANDA |
| Insulation | 8/22/2022 | Partial Approval | JOHNNY MIRANDA |
| Insulation | 9/27/2022 | Approved | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 2/17/2023 | Partial Approval | JOHNNY MIRANDA |
| Final | 3/31/2023 | Corrections Issued | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 3/31/2023 | SGSOV Not Ready | DAVID FEILER |
| Smoke Detectors | 3/31/2023 | Approved | DAVID FEILER |
| ELECTRICAL-Final | 6/29/2023 | Not Ready for Inspection | JESUS PINEDA |
| Final | 6/29/2023 | Not Ready for Inspection | JESUS PINEDA |
| HVAC-Final | 6/29/2023 | Not Ready for Inspection | JESUS PINEDA |
| PLUMBING-Final | 6/29/2023 | Not Ready for Inspection | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 6/29/2023 | SGSOV Approved | JESUS PINEDA |
| ELECTRICAL-Final | 7/12/2023 | Not Ready for Inspection | JESUS PINEDA |
| Final | 7/12/2023 | Not Ready for Inspection | JESUS PINEDA |
| HVAC-Final | 7/12/2023 | Not Ready for Inspection | JESUS PINEDA |
| PLUMBING-Final | 7/12/2023 | Not Ready for Inspection | JESUS PINEDA |
| Final | 7/21/2023 | Permit Finaled | JESUS PINEDA |