3246 S FEDERAL AVE 90066

Certificate Information: 3246 S FEDERAL AVE 90066

Application / Permit
21016-30000-38269
Plan Check / Job No.
B21WL04521
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel (E) Single family dwelling.. Per engineering design.
Permit Issued
Issued on 2/10/2022
Issuing Office
Current Status
Permit Finaled on 7/24/2023

Permit Application Status History

Submitted 10/13/2021 APPLICANT
Assigned to Plan Check Engineer 10/20/2021 ALFREDO JARA
Corrections Issued 10/21/2021 ALFREDO JARA
Plan Check Approved 11/16/2021 ALFREDO JARA
Issued 2/10/2022 APPLICANT
Building Plans Picked Up 2/11/2022 APPLICANT
Permit Finaled 7/21/2023 JESUS PINEDA

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/4/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 11/5/2021 DINAH GARIN
Grading Pre-Inspection Cleared 11/16/2021 ALFREDO JARA

Contact Information

Contractor X3build Inc; Lic. No.: 1065494-B 3163 DONALD DOUGLAS LOOP   SOUTH    SANTA MONICA, CA 90405
Engineer Ilasin,, John Lacebal; Lic. No.: C67469 1011 OARFISH LN      OXNARD, CA 93035

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/16/2022 Approved JOHNNY MIRANDA
Footing/Foundation/Slab 3/16/2022 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 5/3/2022 Partial Approval JOHNNY MIRANDA
HVAC-Rough 6/20/2022 Corrections Issued RICHARD STEINBACH
PLUMBING-Rough 7/11/2022 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 7/28/2022 Corrections Issued HERBERT GIRON
PLUMBING-Rough 7/28/2022 Approved HERBERT GIRON
Shower Pan 7/28/2022 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Rough 8/1/2022 Approved OGANES TARAKHCHYAN
Shower Pan 8/1/2022 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 8/4/2022 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 8/4/2022 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 8/8/2022 Approved JOHNNY MIRANDA
HVAC-Rough 8/8/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 8/15/2022 Partial Approval JOHNNY MIRANDA
Interior/Exterior Lathing 8/17/2022 Approved JOHNNY MIRANDA
Drywall Nailing 8/22/2022 Approved JOHNNY MIRANDA
Insulation 8/22/2022 Partial Approval JOHNNY MIRANDA
Insulation 9/27/2022 Approved JOHNNY MIRANDA
Footing/Foundation/Slab 2/17/2023 Partial Approval JOHNNY MIRANDA
Final 3/31/2023 Corrections Issued DAVID FEILER
SGSOV-Seismic Gas S/O Valve 3/31/2023 SGSOV Not Ready DAVID FEILER
Smoke Detectors 3/31/2023 Approved DAVID FEILER
ELECTRICAL-Final 6/29/2023 Not Ready for Inspection JESUS PINEDA
Final 6/29/2023 Not Ready for Inspection JESUS PINEDA
HVAC-Final 6/29/2023 Not Ready for Inspection JESUS PINEDA
PLUMBING-Final 6/29/2023 Not Ready for Inspection JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 6/29/2023 SGSOV Approved JESUS PINEDA
ELECTRICAL-Final 7/12/2023 Not Ready for Inspection JESUS PINEDA
Final 7/12/2023 Not Ready for Inspection JESUS PINEDA
HVAC-Final 7/12/2023 Not Ready for Inspection JESUS PINEDA
PLUMBING-Final 7/12/2023 Not Ready for Inspection JESUS PINEDA
Final 7/21/2023 Permit Finaled JESUS PINEDA