7032-7034 N WILBUR AVE 91335
Certificate Information: 7032-7034 N WILBUR AVE 91335
- Application / Permit
- 21016-30000-32857
- Plan Check / Job No.
- B21WL04364
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert (E) attached garage of (E) SFD to ADU per GCS 65852.2(e)(1)(A) and WFPP
- Permit Issued
- Issued on 11/2/2021
- Issuing Office
- Current Status
- CofO Issued on 4/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/4/2021 | JASON JANGADA |
| Corrections Issued | 10/4/2021 | JASON JANGADA |
| Plan Check Approved | 10/20/2021 | JASON JANGADA |
| Issued | 11/2/2021 | APPLICANT |
| Building Plans Picked Up | 11/4/2021 | APPLICANT |
| CofO in Progress | 4/18/2022 | VINCENT HANLEY |
| Permit Finaled | 4/27/2022 | MICHAEL SMITH |
| CofO Issued | 4/27/2022 | MICHAEL SMITH |
| Permit Finaled | 4/27/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/6/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 10/6/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 10/7/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/17/2021 | Partial Approval | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 11/30/2021 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 11/30/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 2/10/2022 | Approved | VINCENT HANLEY |
| Gas Test | 2/10/2022 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 2/10/2022 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 2/16/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 2/16/2022 | Approved | VINCENT HANLEY |
| Insulation | 2/16/2022 | Approved | VINCENT HANLEY |
| Drywall Nailing | 2/24/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 2/24/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 4/4/2022 | Approved | VINCENT HANLEY |
| Final | 4/4/2022 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 4/4/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 4/4/2022 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 4/4/2022 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 4/4/2022 | Approved | VINCENT HANLEY |
| Final | 4/18/2022 | OK to Issue CofO | VINCENT HANLEY |